New Stringers – Part III

Welcome back! Apologies for the cliff hanger from the last post, but (spoiler alert) we didn’t get trains running by Memorial Day! Had I not had a dental implant installed last week and been forbidden to do any strenuous activity last weekend, we might have had a chance. But it was not to be.

I just had my follow up visit yesterday and asked about the restricted activity. Good news! I got a pass to continue working on the stringer replacements! I had taken yesterday off anyway to make an already long Memorial Day weekend longer and give a fighting chance of making the deadline.

The new fence is in and it’s time finish up behind the shed. The mainline, switches to the sidings off the mainline, and the sidings themselves are all back in place. All the elevated sections have the track back in place as well. All that remains are the wye and ground segments from the downtown loop to behind the shed.

Reworking The 10′ Diameter Stringers

With the wood stringers it was easy enough to just use the posts to hold everything in position. These PVC stringers aren’t so forgiving. The spacer blocks want to twist, like pulling a candy wrapper on both ends to unwind it. The screws want to pull out of the PVC “end grain”, much more so than wood spacer blocks. We’ll have to glue them.

Easier said than done! Sitting it in the sun to make it “bendy” doesn’t hurt. Thankfully only the one destroyed by the hurricane, now long gone, needs replaced. The other two that remain on the side between the shed and the garage are questionable, but still functional. But before installing the new stringers, those blasted “Asparagus Ferns” have to go!

Not sure who thought these things would be a good addition to their yard, but they are absolutely annoying! Thorns sharper than roses, impossible to eliminate, short of digging them out by the roots. And that’s what was done. Not a single one remains. If one decides to pop up later, it just means there’s a root that was hiding and overlooked.

Memorial Day Weekend Progress

Between replacing the stringers and modifying the design of the new curved turnout, it’s been pretty busy this Memorial Day weekend. But there are still many more stringers to replace. After placing the new 10′ diameter curved stringer, it was apparent the posts had been pulled out behind the shed when the new fence went up. The hope was they could remain in place. No such luck.

Without them in place, more time was spent guessing where those posts actually go than painting and installing the connecting stringers. But at least that’s done now and ready for track. Once it’s repaired that is. Anyone who’s ever used Aristo-craft track and had to deal with those tiny, fumbly 2mm screws knows what a pain it is to remove them just to reseat the rail in the tie strips.

Moving on to complete the remaining straight stringers now that the stringers behind the shed are complete. The diagonal stringer that forms the Main Street crossing is already in place, so the short connector sections are next on the list. Before long they’re assembled and painted and ready to install, along with a new siding extension. So in they go.

New Solutions To Old Problems

I bought a number of rolls of High Temperature PLA (HT-PLA) filament to print my own ties for the curved switch design and replacement tie strips. Other applications include cut stone block retaining walls and brick downtown apartment storefront buildings. As usual, nineteen different projects going at once, if not nineteen thousand!

One other item of note that applies to the wye switch, the curved switch, and the HT-PLA. Previously I had designed and printed insulated replacement parts for the SplitJaw™ clamps on the diverging routes of the wye using standard PLA.  It quickly became apparent that PLA is no match for the Florida sun! Another one of those found out the hard way items.

Essentially the PLA slowly deformed in the heat until the track joints simply gave out and popped open with all the stress those curved wye leg rails are under. Hopefully this recent improvement of HT-PLA will fit the bill. But before using HT-PLA in earnest, it has to withstand the test of the Florida sun and heat. We’ll find out soon enough.

Surprise! Surprise!

Not much surprises me anymore, but I am absolutely amazed at the performance of this HT-PLA! The first test was printing and annealing 8″ long brick walls, fairly thin at ⅛” thick, then leaning them over the 4″ tall half height concrete blocks that make up the station platform and leaving them out in the sun all day. They remained straight and tall, no bending, sagging, or warping!

Next was 4″x7″ black cut stone block retaining walls. Same outcome! As expected, being black, they got hot. Really hot. Like nearly 150°F! I got out the infrared thermometer to measure. It and most of the turf were ~145°F! The darker green turf was even hotter at ~155°F! I don’t know how Rocket can stand to walk on it, let alone lay down on it, but I couldn’t get him to move from there!

Those cut stone retaining walls were entirely another project. I’ll have a post about them to link to soon. Let’s just say it took a number of different false starts just to get something that could be 3D printed. But after a few design iterations, it’s now a viable part of the station siding facelift. Let’s just say I ordered a LOT more spools of HT-PLA filament just for them. Stay tuned for more details.

Progress Continues

Fast forward a few weeks and it’s time to install the wye trackage, starting with the wye switch. The mainline switch and sidings have been installed for nearly a month now. Time to get the track and as much of the wye installed as possible, in anticipation of the new curved switch prototype.

The curved switch design began in earnest the beginning of May, and has slowly evolved into its current incarnation, using HT-PLA for the ties, frog, and throw bar. Even an adapter for the standard Aristo-craft switch machine. There’s even a preliminary version of a servo driven switch machine on the drawing board, now printed using HT-PLA. But that’s yet another project for another day.

The most difficult part of refurbishing the wye is already done, with the exception of figuring out which of the many curved flexible track sections are the two that go there. Actually, a number of them will fit, just not sure which are the right ones. But I’m getting ahead of myself again. Time to fit the wye switch in place. The curves will follow.

While We’re At It

While I was going through the rest of the flexible track sections looking for the wye pieces, I decided to figure out where the rest of them belong too. The original thought was to just get the downtown loop operational to be able to continuously run trains. That’s still a ways off, but the 4th of July will be here before we know it. We’re not missing that deadline!

It took a number of iterations to figure it all out, just like the wye legs did. For now the track’s all just laying on the ground approximately where it goes, waiting for another time to work on it. The remaining parts of the wye need finished before any of it can be connected, so it will have to wait until that’s done first. Then the drudgery of removing what remains of the rotted stringers begins.

Again, that’s not on the schedule. Not yet anyway. Just getting the continuous loop up and running is the goal, and it’s almost a reality. Just a few more things until the first test run! But those things are going to take another weekend, if not two, putting us well into June.

About That Wye…

Setting and levelling the stringers for the legs of the wye takes the entire weekend, but is well worth the effort. More excavation is required, but it adds more dirt to build up the embankment with. Enough dirt that the turf needs pulled up to allow contouring the additional overburden. But I’m getting ahead of myself again.

The turf is two long sections that are way too heavy to lift all at once, covered in a couple inches of leaves and acorns and gravel and already full of trapped dirt. You name it, it’s covered in it. All of it is slowly shoveled off and added to the base of the elevated track section just beyond using just that small, hand sized garden spade. Building up that embankment is slow going for sure.

Beyond that, the turf needs cut from beneath the long straight leg just to extricate it and excavate even more dirt to set those stringers in place. That hadn’t been part of the original plan. But because the turf’s essentially trapped beneath the stringers, it has to be done. Slicing the turf along the plastic edging that defines both sides of the right of way frees it up.

Can’t recall why it was done that way the first time around with just access openings in the turf for the posts. Perhaps the thought was it would reduce the likelihood of rot. The evidence proved otherwise. Perhaps it was more expedient. Certainly paying the time penalty now for that decision in the past.

Earth Moving

Thankfully it’s in a number of pieces, but even those are heavy. They are so heavy with trapped dirt I can barely lift one at all. The trick is to lift by an end or corner and shake the dirt loose into a pile that can then be easily moved where desired. Slowly but surely the dirt is shaken out of the turf, little by little, until the entire length is now laying upside down on top of the embankment.

More dirt needs moved and contoured with the flat shovel to shape the embankment. Posts need persuaded into place using the sledge hammer. Wiring needs rerouted and buried along the newly created “trenches” the stringers now sit in. Last but not least is cutting the remaining turf to fit the new topology. It’s exhausting work, in the midst of a heat advisory, but well worth the effort.

The embankment finally looks like an embankment. The wye finally looks like a wye.  And best of all, it looks like it’s meant to be that way. Not an afterthought. Not a pile of dirt under the raised track section. Ann was not very happy about all that dirt at first, worried about slipping on it and falling while stepping over the tracks. But now she says it looks great, like it’s supposed to be there.

Unveiling The Curved Switch

Fast forward another weekend and it’s finally time to test out the prototype curved switch. At four feet long (~122cm), it’s a bit unwieldy. Getting it from the workbench and out the back door to the wye was a real feat, but it fits like a glove! Perfect! Can’t wait to see whether it works or just derails everything.

For now, just the 14′ diameter diverging route is connected to the North curved leg of the wye, but the 20′ diameter route provides the starting point for laying down the straight leg of the wye. The track for the other side of the curved switch can now be put back in place too.

That much needs to be completed to be able to lay the rest of the ground level track up to and around the curves behind the shed. Hopefully it’s apparent why starting from that mainline switch and working the wye and the rest of the track from there is mandatory.

Growing Pains

We’re using standard SplitJaw™ rail clamps on the mainline side of the wye switch and our homebrew “double” insulated clamps on both the diverging routes.  In this case, double insulated isn’t meant in the sense of power tools, but rather a double length rail clamp, using four screws where the standard clamps use just two. Lots of growing pains there.

Every time I look, the dogs have once again pulled the joints loose or broken the clamps altogether! The prototype didn’t allow them to tighten all the way. Subsequent versions using annealed HT-PLA just didn’t have the strength. Many design iterations later they finally survive the constant pounding of fetching the ball and chasing the squirrels. Double insulated and now double thick!

And now that the rail clamps keep everything together, all the track moves together… Right off the stringers! This is going to take more than wire ties to keep the track aligned and remain on top of the stringers. Going to have to think about that one. First thought is something like the deck sections that hold the track in place for the station siding. We’ll revisit that later.

Growing Trackage

The curved switch is designed to replace a full 14′ diameter section (22.5°) plus an additional 1⁄3 section (7.5° – grand total of 30°). If geometry and angles aren’t your thing, it takes sixteen of the 14′ and 20′ diameter sections to complete a circle. It only takes twelve of the 10′ diameter sections (each section is 30°). The curved leg of the wye is a single piece of flex track just the right length.

Long story short, there are three remaining 14′ sections to place after the switch points bringing us to point due East. Those 14′ sections connect to two 20′ diameter which turn us Southeast. Those connect to two 5′ long straight sections, running diagonally across Main Street. A short connector section joins to another set of two 20′ diameter sections that bring us back to due East.

From there a 2′ straight section connects to three 10′ diameter sections, bringing us due North behind the shed. The mainline also crosses Main Street, but perpendicularly. It then connects to another set of three 10′ diameter sections, again bringing us due North behind the shed.

All Coming Together

It’s all coming together rather nicely. The only missing trackage is the 10′ diameter curves and the straight sections to connect them behind the shed (and all of the lower loop around the deck). I didn’t think I had enough of those 10′ diameter sections left that could be repaired, but it appears I was wrong. There were enough for all but one quarter circle, made up with flex track.

The remaining straight sections behind the shed will need cut to fit. Time to break out the tape measure, Dremel saw, and diamond files. Might also need a few new tie strips to hold the rails in place. My skills with the Dremel saw leave much to be desired. Nothing a diamond file won’t fix, but need to start thinking about designing and 3D printing a “chop saw” jig for making precise cuts.

That completes the entire continuous loop of track. It’s been a long time when we could last say that. With that much done, it’s time to turn to the wiring. But it’s already getting late on yet another Sunday out in the heat advisory weather. The wiring will have to wait for next weekend, along with running trains. As much as I’d like to test the track, patience is prudent.

At this point. it’s almost like starting over with the wiring anyway. Thankfully all the fuse positions and most of the cables are labelled, albeit upside down on the fuse box and weather faded sharpie on the cables. The three new wye cables aren’t labelled at all! Need to break out the multimeter and start testing. Next weekend.

Question? Concerns? Leave A Comment!

If you have any questions or concerns, please feel free to comment on this post. In any case, you’ll need to create a user account to do so. We don’t use any personal information for marketing or to spam you (see our privacy policy). You’ll receive a verification email. Reply to the link provided to verify your email address. It’s all automatic. No waiting on moderator approval! No spamming your inbox with useless advertisements and “Special Offers”. None of that nonsense. We do it this way to prevent bots and spammers from detracting from your experience.

More to come. Stay tuned for Running Trains!

 

Making Realistic Cut Stone Retaining Walls

Welcome back! This is the story about achieving our long time goal of 3D printing realistic cut stone blocks. For the longest time it was out of reach, mainly because of my limited abilities, coupled with the limitations of the tools I’m using to capture the designs. But renewing the search to find new approaches to solve the design problems finally paid off recently!

Before we dive right in there’s some history we need to cover. It may seem like the long way around, but some backstory helps describe the problems looking for solutions, and the journey to find them. This all started long ago when we decided to use the concrete patch casting method for the walls of our Downtown Marketplace buildings.

We were off to a good start, learning from the mistakes of the first casting, and made two more. Painted, weathered, and detailed with 3D printed windows, doors, and display cases, they were impressive. We used mortar to attach them to concrete blocks for added strength against the Barkyard’s marauding German Shepherd population. Then other priorities stole us away.

I wanted to give proper credit where it’s due, but I’m sad to say the original site (rrstoneworks.com) I used as a reference for this technique is no longer online. They sold plastic pattern sheets and actually sliced real stones into what they called “Stone Sticks”. I have two boxes of them, with no way to get anymore of them. Need to check the “Wayback Machine” for anything useful…

It didn’t take long to realize the 3D printed PLA parts weren’t up to the task. The final nail in the coffin was the grand experiment, the Grand Hotel, also 3D printed from PLA. It lasted only days before it warped, got brittle, and fell apart. Another failure. The only thing durable enough to last over the years were castings. We detailed what it took to make that happen in this old post.

A Bit Of History

Fast forward a bit to casting retaining walls for the track to climb the grade it makes along the back fence and around the corners. We’ve already moved a LOT of dirt to create the embankments with the proper slope that sits beneath the tracks to support the retaining walls, pretty much following prototypical practice.

Struggling with designing casting molds for weeks, then months, the final version is still lacking years later. It lacks a definitive means of supporting the walls and connecting them together in a rugged fashion. It lacks a mechanism for adding on new segments to previously placed ones. Most bothersome is the lack of detail in the large, cut stone blocks that make up the wall.

The idea was to pour concrete into forms that would capture the castings and hold them in place while the concrete hardened then remove the forms. The design progressed about this far, printing mockups, and assembling them to help visualize what we’d encounter when doing this for real with mixed concrete ready to pour, detailed in this post. It was overwhelming. The design was tabled.

More Backstory

Fast forward a bit more to casting concrete roadbed bricks. Another learning process. Another shelved approach. The original approach was to form and pour in place, then “screed” the ballast profile into the wet concrete, like those concrete curbing machines do. That proved to be a lost cause, perhaps because the mix wasn’t wet enough, perhaps because I’m a novice and not a Mason.

The next iteration was to create a long mold to cast individual “bricks” from the concrete. Screeding the top flat was much easier than trying to form a profile shape, but setting up the mold with all the pieces in place then cleaning up the mold afterward was tedious and time consuming. The mess of pouring concrete and the strenuous effort of mixing it adds up to more effort than reward.

Another drawback to any sort of casting is the amount of time involved, beyond the preparation and effort. It’s a series of “hurry up and wait” events that have to occur within a fairly strict timeframe. Once mixed, the pour has to occur quickly afterward. Then wait at least a day but not much more than that before removing the green castings from the molds. Time to find another way.

New Solutions To Old Problems

Previously I had designed and printed insulated sections for the SplitJaw™ clamps on the diverging routes of the wye. It quickly became apparent that PLA is no match for the Florida heat! Essentially the plastic slowly deformed until it simply gave out and the joints popped open with all the stress those curved legs of the wye were under. Another found out the hard way item.

Even PETG struggles with the heat. Nick was having similar issues with 3D printed parts for his “under hood” automotive applications, but he found a solution, High Temperature PLA (HT-PLA). He printed a set of coil mounts with it to test how well it stands up to the high temperatures in the engine compartment. The parts need “annealed” first though to give them their heat resistance.

As a test, he annealed one mount but not the other, then installed them on the engine. One melted. One did not. Needless to say annealed HT-PLA passed the test. He swapped out the melted one with another annealed one and they’re still going strong. I bought a roll of black HT-PLA filament a while back to see if this recent innovation will fit the bill for our needs too.

New Opportunities For Old Projects

The bench space issue in the garage has delayed further casting, waiting for the bench to be cleared off, literally for years now. The reason for castings is twofold. First is durability when faced with constant pounding from three German Shepherds. The second is resistance to the brutal Florida heat and environmental challenges in general. Concrete holds up better than wood or PLA.

PLA lasts only days before warping. We found out the hard way with the Grand Hotel “skin”. We need a quick way to test this HT-PLA in the baking hot Florida sun. The quickest way there is to print something we’ve already designed, like one of those brick walls from the Downtown Marketplace stores. But instead of manually editing it to make it thicker, it’s time to try out OpenSCAD.

What better test for something that’s an exhaustively “manual intervention required” task than laying out a brick pattern? In a little over an hour the OpenSCAD model is rendered, exported as STL, and printing! While that’s printing, it’s time to learn even more about OpenSCAD and make the hard coded preliminary model more parametric.

Parameters like how tall and wide is the wall? How many windows? What scale? Brick dimension? Adding those features took a little more than a day to resolve, but now it’s totally configurable and can even create Downtown Marketplace storefronts! Just flip the switches and change the values and render another model, then export the STL and print!

Test Time

Before going any further with the grand experiment of HT-PLA, we need to test whether it will perform as required. I expect it to perform as well as it did for Nick. The first brick walls were printed using red HT-PLA. They were then annealed at 100°C (212°F) for 30 minutes as recommended by PolyMaker, the filament manufacturer, and allowed to cool back down slowly in the oven.

Glad I saved the “Easy Bake” toaster oven from the scrap heap. The only thing wrong with it is the broken handle, quite the nuisance when dealing with that hot glass door. It still works fine though. And it’s old school! Everything’s set using dials, including one of those timers that winds up and slowly ticks away, counting down to DING! It’s done. No modern computer crap to fail.

Once annealed, I set the walls out in the sun all afternoon, standing against the half high concrete blocks, where they can bend at about the halfway point under their own weight if they’re going to. Thinking the oven was plugged in when it wasn’t, the first brick panel didn’t get annealed, creating a side by side comparison test similar to Nick’s. That panel warped slightly into a convex shape.

But the rest of them passed the test with flying colors! WOOT! They’re only ⅛” (~3mm) thick and no deflection whatsoever! No warping. No distortion. No discernable changes at all. Nothing. Absolutely amazing! I tried re-annealing the warped one using a weight to try to flatten it back out, but it just warped into a concave shape this time. Oh well, at least now we know what to expect.

Riding The Wave Of Success

It’s the convergence of multiple successes coupled with a potential solution to the heat resistance problem that prompts pulling the cut stone retaining wall design out of mothballs. A quick search online reveals a post on the Model Railroad Hobbyist forum by Glenn Butcher about his solution to the exact thing I’m looking to accomplish! What are the odds?

At first glance it’s way too overcomplicated as a quick solution, but then I see that Glenn has already created 20 textured stone STL files, and in OpenSCAD no less!. Now that’s the ticket! Without getting way too technical, he generated “height maps” to use as the textures using a technique the makers of Star Wars used to generate realistic, computer generated terrain.

In fact, the approach is captured in a publicly available library, libnoise, that anyone can use in their own programs. That’s exactly what Glenn did then shared his work, noisetool, online. Sounds good, right? The drawback is those height map files for OpenSCAD are tens of thousands of lines long. Each. Now put 20 of them in one program! Good luck scrolling through something that big!

Making It Work

I know, engineers, right? I thought I over-engineered things, but Glenn takes it to a whole new level. That’s a good thing! Each of these textures is meant as a 3″ x 6″ HO scale wall, but our cut stone blocks are ½”x1″, a 6:1 scaling factor. If we want one out of six in two directions, 6 x 6 = 36, and we only want one of them. We could throw out 35 of 36 values and still have plenty of detail.

In an attempt to work around pasting all those huge files into OpenSCAD and simply import a series of 20 files that captured each of those height maps as solid models I used an online tool that converts STL to OpenSCAD files to be able to import those 20 STL files as modules I could include in OpenSCAD and then arrange them programmatically.

I get it all working up until I try to actually render it to export the STL and get a “Thrown Together” error for every stone! Not sure what that means or how to fix it. A quick search says I should try a development version newer than the 2021 release version. I don’t have the time to throw at getting a development version of the program working. This was supposed to be a quick win.

Next!

Well that was a LOT of wasted time for absolutely no reward! Time to get it working in SketchUp. I imported the series of 20 STL files that captured each of those height maps, one at a time, into FreeCAD. Once there, I created a mesh from the STL, optimized the mesh, and then created a solid from the optimized mesh and exported them as .dae design file models SketchUp understands.

Alright, I promised I wouldn’t get too technical, but it’s worth noting how I created the models. Rather than write a program to sift through all that data and throw out what we don’t need, I just pulled the solid models exported from FreeCAD into SketchUp. From there they’re scaled and the stones manually arranged into our familiar 4″ x 7″ retaining wall segments.

Next HT-PLA test, black cut stone retaining walls. If anything doesn’t stand up to baking in the hot Florida sun, it’s black anything. Anyone who has a black car interior knows how scalding hot those surfaces get after baking in the sun all day. Can’t even touch the steering wheel for minutes, even after the A/C is blowing cold on it, and even then you wish you had gloves.

Adding Realism

It takes some time to get all those stone models imported and resized to fit our existing retaining wall dimensions. It’s soon apparent there’s WAY TOO MUCH DETAIL! What used to be snappy response times are now so sluggish I’m wondering if I actually pressed the key or clicked the mouse. In any case, I lay out a pattern of blank, mock stones then replace them with the imported ones.

One by one I substitute the textured stones until I’ve used all 20 of them, the first three courses out of eight. The next three courses I start at the beginning again, but flip them along their green (Y) axis, from left to right, effectively making them a mirror image of the originals. The last two courses use a similar approach, except this time flip along the red (X) axis, mirrored from top to bottom.

That leaves the “half” blocks at the end of the staggered courses. I chose a handful of stones that look the flattest, with the least amount of detail, because sizing them to half their length will stack twice as much detail in the same amount of space. It works out well and the mock half blocks are replaced with the actual stone models in a similar fashion to the full blocks.

There! Now we have a “flat” wall with realistically textured cut stone blocks that we can test with. Well, once the STL is exported, sliced and 3D printed we do. First it goes into the Easy Bake oven to anneal. Then it’s punished by the Florida furnace. Fingers crossed this will hold up to the heat. The flat wall passes with flying colors! It sat out all day, then overnight, and again all the next day.

Testing While Adding More Realism

Meanwhile I’m working on making the flat wall sloped to match prototypical construction. When I say “flat” I mean the blocks are stacked directly on top of the course below, with no lean either way. The prototype calls for an inward lean to account for the increasing forces exerted by more and more dirt the deeper down it goes. The sloped profile is more realistic than the original flat version.

Each new iteration of the evolving design gets printed and added as a new test subject. All the black test subjects have been baking in the sun all week with no discernable changes. Absolutely awesome! That means using the HT-PLA for tie strips is a possibility too! Time to try printing the switch ties for our new curved switch with it.

Another practical use is rebuilding the Downtown marketplace using HT-PLA instead of castings. It may not save much time over castings, each 5″x8″ wall segment takes hours to print, but it’s far less messy! And it certainly doesn’t take as much prep and cleanup time as casting. But we’ll save all that for another post.

Some Caveats

There’s something to be said for getting it right the first time. Something that seldom happens. I have a bin full of useless prototypes that didn’t make the cut. May as well get used to burning through at least a 1kg spool of filament prototyping a design to get to the production version. Or should I say a production version? There’s always that one last tweak to add…

Each part of this design has evolved to suit the requirements of the station siding, and now by extension, the ever evolving station platform. But I’m getting ahead of myself again. The initial design elements are primarily the walls and pillars that join them together, the track deck and capstones, and the underlying frame that ties everything together around the stringers.

Originally the walls were glued to the pillars. More like solvent welded, similar to using plastic model cement. But it quickly becomes obvious after about four wall panels that a wall 10′ long can’t easily be moved all together all at once without breaking apart. Time to rethink the design. So now everything is modular, held together using M2.5 stainless steel socket head cap screw hardware.

Modular Design

That four wall panel section is still sitting on the office book cases. I just can’t bring myself to throw it away yet. Why four panels? Because that’s the magic number of roughly 8″ (~20cm) sections it takes to make a complete 10′ diameter track section. The pillars are designed to angle each wall panel from the last by 7.5°. Four gives a total of 30°, the extent of a 10′ diameter curved track section.

Two M2.5x6mm screws hold the pillar to each wall panel, a set for each panel on either side of the pillar. The transition to tangent track and remaining walls have another pillar design that has no included angle so the wall panels remain straight and parallel to one another. There is one exception for the inside transition from 10′ diameter, mainly to accommodate track deck mounting.

The track used to sit directly on top of the stringers, but now it sits in a “trough” in the track deck, as deep as the ties are tall. The “floor” of the trough the ties sit in is ⅛” (~3mm) thick and now sits directly on top of the stringers. The track is not mounted down to the track deck, but rather left free to “float” in the trough, and the track deck itself mounts to the underlying frame.

Keeping Things Where They Belong

The frame surrounds the stringer, the main reference for track placement, holding things together and where they belong relative to the stringer. The frame is a three piece design. Two tall sections that mount to the back of each opposing wall pillar using two M2.5x8mm screws. The third “Twist Lock” piece pulls the opposing mounts together and locks the assembly around the stringer.

Leaning the twist lock back at an angle allows the set of “hooks” at the bottom to catch and hold just inside those two mounts, then by twisting it up into position, it locks everything together, including the wall pillars. The twist lock section is secured to the mounts using two M2.5x10mm screws from the top, mainly because that’s about the only access left once everything’s assembled.

The track deck itself mounts to the underlying frame using four M2.5x10mm screws, covering and blocking access to those two screws securing the frame pieces together at either end of the deck. The socket heads are recessed into the raised portions of the deck on either side of the track that forms the trough. Eventually they will be concealed by a fence, roof supports, or some other cover.

The capstone strips are secured to the deck from beneath using M2.5x16mm screws. Once the deck is mounted to the frame, they are no longer accessible. The single, larger pillar capstones can be held in place by simply inserting their built in tabs into the slots in the underside of the deck capstones. They can also be secured using button head cap screws, but it generally isn’t necessary.

New Challenges

With enough 10′ diameter sections in place to account for the surrounding grade increasing to meet the track level and the kinks in the transition to tangent track hammered out, it’s time to think about the station platform and how to connect it to what we have so far.  More specifically, how to incorporate the old station platform 4″x8″x16″ half height concrete blocks into the new design.

The whole sad story about how nothing’s left of the original station platform was left out of the earlier history lesson. The abridged version is there used to be raised bed planters along the entire length of the patio. Those blocks sat between them and the track stringers, with a roof of sorts from the planters above acting as a covered station platform.

The planters were removed long ago, leaving just those blocks along the station siding track. Because the track sits roughly 4″ off the ground, any kind of platform would need a good bit of support or dirt fill beneath to hold up to the constant pounding from the pups. We already have all those blocks just sitting there anyway, so why not incorporate them into the design?

Transitioning From Curved To Tangent

Before we can use those half blocks, we have to transition from the curved approach to tangent (straight) that will become the station track alongside the platform. This is the exception for the inside transition described above. The exception it refers to is where the curved track deck meets the tangent track deck.

Originally the thought was to have a transition track deck and transition pillars. Partway into that design it was discovered that not only would it take one transition track deck, it would need two of them and both of them would be different! Basically one to go from 7.5° apart to 3.75° apart, and then from 3.75° to straight and corresponding pillars to match. But that didn’t make sense.

The current design simply reuses the curved and tangent track decks along with a regular 7.5° pillar outside and the new transition pillar inside. The inside transition pillar has a 7.5° angle too, but the stones are offset from the middle of the angle to account for the track deck mounting locations. I feel like I’m waving my hands again, but this gets us from curved to straight using fewer parts.

By shifting the mounting points on the inside transition pillar to accommodate the standard track decks, it eliminates the need for at least three or more additional, specialized parts, only useful in this one situation. Too bad I didn’t think of it before designing a number of those specialized parts first and then having to toss them out after wasting all that effort.

Transitioning To A Platform

So now that we’ve transitioned from curved to straight, before we can use those half blocks, we still have to transition from the current approach track with retaining walls on either side to a platform with a retaining wall on one side and a station track on the other, the station track with its own retaining wall on the other side, continued from that side of the approach track.

Hopefully the “see through” panels give a better view of how all these 3D printed parts come together to give the illusion of a believable scale model. For me, seeing them slowly come together and become what I’ve always dreamed of seeing is more than satisfying. It truly is a dream come true. The black and gray colors aren’t very realistic, but until the design is finished, it’s good enough.

The design must account for the inside wall changing direction, in this case perpendicular to it. In order to widen the footprint and conceal the half blocks with something that looks like a station platform, we need a different inside transition pillar, plus an additional outside transition pillar to redirect the wall back to the original approach wall direction along the side of the platform.

Unfortunately, because of the dimensions of the half block in that direction, we can’t use the standard 4″x7″ wall connected to all the other pillars. Altogether they add up to 8″ total, too short to wrap around the 7⅝” width of the block. We’ll need a 4″x8″ wall to allow just enough clearance for that block width.

Expanding The Design

So now instead of two opposing wall pillars separated by the width of the track deck one of those frame mounts will now connect a “hidden wall” section to the opposing cut stone wall. These hidden wall sections will mimic the cut stone wall dimensions along with their own pillars. They connect to a widely separated cut stone wall pillar on the other side of the block every 16″.

Because the block is actually only 15⅝” long, that leaves just ⅜” to work with. The connecting frames between the hidden walls and far cut stone walls are only ¼” thick, leaving barely enough room to spare. It’s a tight, snug fit, but it anchors everything and supports the platform sections. Each section is still only 8″ wide because of 3D printing build volume and “Easy Bake” oven limitations.

Two platform sections are joined together and fitted 16″ at a time. A “stub” mount for the platform sections is used in place of a connecting frame section where the block length is in the way. This ensures the hidden and far cut stone walls are still rigidly secured together even where a connecting frame member can’t be placed.

Adding The Station Platform

The track deck still mounts to the twist lock frame, but now only one of the capstone strips is needed for the side opposite the platform. The platform design itself takes some thought about how to make a believable scale model that doesn’t have obvious separation “cracks” every 8″.  Why not a brick herringbone pattern framed by what appears to be stone blocks?

OpenSCAD to the rescue again! It takes a bit longer than expected to perfect the design, but it’s a believable herringbone pattern, centered about all four sides. It even has mounting holes to attach a support frame that the framing stone block strips will also attach to. Those stone block strip designs are captured in SketchUp along with an imported version of the brick herringbone piece.

To facilitate the modular design concept for adding new sections, the edge of the new platform section will simply slide in beneath a previously mounted section without need for mounting screws. If anything, loosening the existing mounting screws that hold the previous section may be necessary. Then both the old and new platform sections can be tightened down together.

One last “transition” design item is necessary for the first platform section along that 4″x8″ wall. There is absolutely no room for any mounting hardware to fasten the edge of the platform to the wall beneath. The half block butts up against the back of the wall to fit everything in the limited 16″ space. Instead, a set of tabs on the first platform subframe slides into slots on the transition pillars.

Assemble, Rinse, Repeat

After that first transition section from the approach configuration to the platform configuration, it’s simply a matter of adding on another 16″ platform section to the previous. Expanding from first platform section to the third doesn’t happen overnight, but it doesn’t take long since I’m printing most of the parts while redesigning the ones that aren’t working as expected.

The only limiting factor on the platform expansion is how long it takes to 3D print all the parts, anneal, paint, and assemble them into the next 16″ section. It takes a lot of parts! Four each retaining walls and pillars, two each hidden walls and pillars, twist lock frames, hidden frames, platform decks, platform subframes, deck border stone sets, track decks, and track deck capstones.

I’ve tried to capture the estimated print times of all the parts when slicing them. Let’s see how well I did and whether I can add them all up for a rough estimate of print time. Add at least another hour to anneal each print, although the last part printed can be annealed while the next is printing. Then add painting the annealed parts and assembly time. It all adds up. But progress is progress.

Color Considerations

Our color palette in HT-PLA is fairly limited, even more so than PLA. Just the basic colors. While the capstones could have been printed in white, the single ACE cabinet only has four slots it and would mean having to constantly swap between white and one of the other four colors, namely black, brown, gray, and red.

Gray was chosen with the idea that the red is too bright for bricks and would need painted brick red anyway. The track deck and capstones can be painted concrete and light stone colors. The black cut stone walls don’t need any paint, but should probably have some sort of UV protection painting the other parts offers, and perhaps a wash with a lighter color to bring out the details.

After an extensive Google search for matches to the Model Master “Aged Concrete” color from my HO scale days, satin Dover White and satin Ivory are chosen for the concrete and light stone colors. At first, they look like they’re same color, but later spray paint batches aren’t as close. Natural variations in stone colors? Plausible explanation if anyone asks. LOL.

Brick red is brick red. Alright, there are variations to be sure. I even made brick color selectable for OpenSCAD, brick red or creme (beige). I’ve seen many modelers design and print painting masks to expose “random” bricks and paint them slightly different colors to mimic the natural color variations. I know I’m a rivet counter, but I haven’t made it to that level of obsession to detail (yet).

What’s Left?

The station platform is slowly expanding. The original platform was 16′ long. Now it extends beyond the end of the patio, so approaching 20′ maybe? So far we’re about half way done, right at the end of that first 10′ stretch of flex track. We can add another 16″ section every couple of days in production mode, pretty much 3D printing parts 24/7.

I’ll wake up in the middle of the night and kick off another if the previous print’s finished. Sometimes I’m a sound sleeper though. But it only delays the inevitable, kicking off of the next print once I’m able to. So far I’ve only screwed up twice trying to go faster than I should have.

First was forgetting to put the PEI sheet back in the printer and frantically killing the print before it could cause more damage. I’m missing a small chunk of the magnetic material that holds the PEI sheet to the build plate after that little fubar. Kicking off another print while the previous one was still sitting in there on the PEI sheet was another. “Why’s it making that clunking noise? OH SHIT!”

I can laugh about it now, but it certainly wasn’t all that funny at the time! Getting back to what’s next, the end panel of the platform still needs designed. Similar to the transition to platform configuration, now we get to the terminate the platform and need to finish it off with walls and pillars that connect the retaining wall together. We won’t have the luxury of tabs and slots this time!

Future Reference

Observations for future reference – overlaying two stone textures atop one another gives a much more realistic looking stone face, but not sure how to “add them together” in a usable fashion. Maybe someday. This is mainly a note to my future self when revisiting the stone texture design. It’s strange that when I rendered the imported stone modules this time it didn’t error out. WTF?

I’ll update this post periodically with progress toward completing the station platform. For now, I just want to get this posted. I’ve been so busy doing so many things it seems impossible to both do and post. I haven’t looked at editing a video in months. Everything takes time and right now the focus is getting the trains running and restoring the previous “luster and glory” of the Barkyard RR.

I have to say I’m pleased as punch with the outcome of this project! It’s been a long time getting here, but it’s worth the wait for the result! All the projects I put on hold are slowly coming out of mothballs. All the things I’ve put off for so long are finally coming to fruition.

In the past I worried about prioritizing things that needed done first. Anymore, I just do what’s staring me in the face, then ask myself, “What’s next?” and just do it. I kind of have to since I do things like buy a bunch of clearance Aristo-craft stuff that’s not in the best condition, then have to design and 3D print replacements for all the broken and missing parts while juggling 19 other projects.

So far so good, but that’s another story.

 

Disclaimer – Not Sponsored

I should mention that the Barkyard is not sponsored by AnyCubic, PolyMaker, Elegoo, Sunlu, or any of the host of other manufacturers of 3D printers and filament or any other entities, like Harbor Freight. I don’t think they’d care much for my nicknames for them anyway, like Horrible Freight, Hazard Fraught, etc. No freebies or evaluation promotions here. This is all paid for out of pocket.

 

Question? Concerns? Leave A Comment!

If you’re interested in obtaining the STL files to print your own block walls, leave us a comment and we’ll be happy to provide them to you. Also, if you have any other questions or concerns, please feel free to comment on this post. In any case, you’ll need to create a user account to do so. We don’t use any personal information for marketing or to spam you (see our privacy policy). You’ll receive a verification email. Reply to the link provided to verify your email address. It’s all automatic. No waiting on moderator approval! No spamming your inbox with useless advertisements and “Special Offers”. None of that nonsense. We do it this way to prevent bots and spammers from detracting from your experience.

More to come. Stay tuned!

 

Making A Curved Turnout – Part II

Welcome back! This is the second part of the curved turnout series. If you haven’t seen the original post yet, you may want to start there first. A good part of this discussion relies on topics covered there already. So where did we leave off? That’s right, the new spool of filament wasn’t the best. The brittle nature of the filament is causing problems with prototype fitment and development.

Its brittleness coupled with a lack of complete support removal is a sure way to snap the foot clamps right off when attempting to test fit the rail. So one more refinement will be to back them off another 10 thousandths as well as raise them all by 10 thousandths. It’s also a vote to just reprint those other ties strips using the other design refinements so far.

But that’s not as easy as changing one model to fix all of them like it was with the diverging route ties. Every one of those remaining switch ties is unique. There are 48 of them altogether. This is where SCAD or other parametric CAD applications shine. Need to nudge everything in the same direction? Simply update that parameter and rebuild the model.

For example, to increase the distance between the tie and foot clamp, it’s a simple change to increase that parameter and rebuild. Not so much with SketchUp. It’s all tedious, time consuming manual effort per clamp per tie. I suppose I could have used a component to model the rail foot clamps, where changing it once would affect all instances, but it wouldn’t account for other factors.

Why Not FreeCAD?

As much as I’d like to put this design in FreeCAD, I keep falling into the speed trap. The speed of implementation trap that is. I already know how to do just about everything in SketchUp and how to workaround things it doesn’t handle gracefully. For me with FreeCAD, it’s at least a Google search, if not another lengthy tutorial video just to learn the basics.

There may come a day I don’t feel the time crunch, but today is not that day. I need to put this new printer through its paces to verify everything is working, and working the way it should. Like most warranties, they’re for a limited time only, plus I want to get rid of the shipping box I’ve been saving in case it needs sent back. The sooner the better.

What new printer? It’s an AnyCubic Kobra S1 Max Combo. It arrived about a month ago and I’ve been waiting for it to get here since I ordered it around Thanksgiving last year (2025). It has a build volume of 350mm x 350mm x 350mm (13.77″ x 13.77″ x 13.77″) and can print up to four colors with the single ACE cabinet version I bought. With more ACE cabinets, it can print up to 16 colors.

All that being said, now I’m paying the time penalty for using SketchUp, which means having to revisit every single one of those rail foot clamps, adjusting them one by one, for every tie. I marked the ones I had to adjust from the initial 17′ diameter tie placement and stretched to fit the 14′ and 20′ diameters. Thankfully I also marked the ones I had to adjust for interference.

Moving Forward

Now the question is whether to just save the current version as a prototype fallback and make the changes to a new version or press ahead blindly. The latter is what I got without even thinking about it. Now I’ll find myself unable to rewind to a previous version later. SketchUp is unforgiving when backtracking to a mistake made many operations ago.

On the plus side, reprinting all those tie strips means I don’t have to finish cleaning up all the rest of those supports! There are few more things I’d like address while I’m at it, like how to mount the frog to the tie strip. The screw placement and openings for the mounting hardware need laid out. If I print things in the same order, I’ll have time for that while the others print.

Another thing I need to look at is using spiral vs. rectilinear top surface texture when slicing to 3D print. The former leaves a pattern that resembles wood grain and the spike head details are visible, but the “diagonal corner” is unrealistic. The latter is smoother, but those spike details are missing. There may be a way to tell the slicer not to rotate 45°. If there is, I certainly haven’t found it (yet).

This will sound like nonsense to folks who aren’t familiar with 3D printing, slicing in particular. Hopefully this isn’t too basic, but 3D printers do their work a layer at a time, building each successive layer on top of the previous one. The slicer effectively slices a 3D model into layers, hence the name slicer. It tells the printer what each layer looks like and how to print them using GCode format.

The Slow Grind Of Rework

Reworking the rest of those tie designs is a chore. A chore I’m not looking forward to. Hours and hours of zooming in on each an every foot clamp on each and every tie for days on end. Thankfully my motivation hasn’t failed me, printing the fruits of my labor while pressing on to finish the next section. Unfortunately it’s finished printing the previous section long before the next is ready.

I knock off “early” the first night at 11:00 PM, knowing the guys will be here bright and early the next morning to put up the new fence around the Barkyard. But that’s a different story for another time. By the end of the second day I finally have all the parts printed again, including the frog, now with mounting holes and wing rails.

Speaking of the frog, that “SketchUp is unforgiving when backtracking to a mistake made many operations ago” was spot on. I had already reworked the hold downs on one side, effectively half the frog modified, when it became apparent there was a major mistake made many operations ago. Sometimes this free program is worth exactly what I paid for it… Nothing.

Feeling Froggy

So as not to lose anything I had done so far, I copied the frog to another drawing and began the tedious “Undo” process back to the single misstep that caused the problem. This is where the history of operations is so valuable in other applications like FreeCAD. Made an error? Just go back and fix it and the change propagates forward without further impact.

Not SketchUp. Rewind then redo EVERYTHING since the mistake. Thankfully I caught it with only half the frog reworked. After that adventure, I was very careful to check my work frequently, especially when adding the guard rails to the frog tie strip section. But that’s the last design to finish for now and it’s printing, with an estimated 6 hours and 39 minutes to go.

While that’s printing I’m test fitting the previous section, the closure rail tie strip, and run into a fitment issue with the last three ties before the frog section. Even though I centered the hold downs around the 14′ diameter stock rail in the design, they’re a very tight fit, like they’re offset too much toward the middle of the tie. I mark them with a red dot in the design to keep track of these fitment issues.

Test Fitting

I’m wondering if it’s just that one piece of rail that has an excessive bend at the end, but then how did it fit through all the rest of the ties with no problem? Why these last three ties? We’ll just keep that in our back pocket for now. This is just the prototype, and only the second iteration for that matter.  I did find two other oversights that I’ve already corrected though.

One is a missing strip section between ties and the other a missed section of a tie on the end to finish making it solid. Not bad for a prototype, and that’s what this stage of development is for, to catch any hiccups before devoting to production… with a whopping production volume of one. Maybe two if I make a mirror image and use it on the other leg of the wye.

After allowing the frog tie section to cool when it finishes printing, the test fitting continues. The rails slide right in with ease, through all the tie strip sections, with the one exception of the closure section already mentioned. The rails fit snugly, yet loose enough to easily assemble. The redesign paid off. Totally worth the days of effort!

Next Steps

I’m impressed with the new printer. Only had one issue with it so far, and a self-inflicted one at that, a clogged nozzle. It’s my fault for using that old brown filament that’s been sitting out collecting moisture and dust, a surefire way to clog a nozzle. The filament became very brittle toward the end of the spool and ended up leaving broken pieces throughout the system when rewinding it.

At least now I know where to look for filament issues, how to take everything apart, and how to resolve them in the future. I ordered a couple replacement nozzles just in case a future clog can’t be cleared. It was a frustrating couple of hours though while I struggled to figure it out. Hours better devoted to redesigning and printing the latest iterations.

Next is testing multi-color printing. The multi-color slicing by height feature works well. And it’s all automatic! No pausing mid print to manually swap filament then resume. I may want to adjust the “flushing volumes”, if that’s even possible. That’s the amount of plastic “pooped” out to be sure the previous color is flushed and replaced with the next color before printing with it.

Thankfully AnyCubic was kind enough to include the print files for a “poop bucket” in the printer’s memory so I didn’t have to design it myself. It’s HUGE! It takes up nearly the entire print height and used more than half a 1kg spool of filament! But now I don’t have to worry about the piles of plastic poop accumulating on, around, and under the old printer anymore. It can make quite a mess.

Behold! The Magnificent AnyCubic "Poop Bucket"
Behold! The Magnificent AnyCubic “Poop Bucket”

Decisions, Decisions

Only ten days in, that’s where we’re at with our curved switch. All that’s left is “finessing” the rails to the proper lengths and shapes. I’ll need to bend a set of rails to the proper radii to start with. The stock rails are fairly simple, but the remaining rails need cut to size for the point, closure, and frog sections. Then grinding the point and stock rails to size. Lots of fun… Not!

I’m already thinking about how to go about that rail shaping. I don’t have a wheel or belt grinder. A Dremel with the proper grinding stones is about the only thing I have on hand. There’s still so much work to do in the garage to make space for anything on any bench that my options are limited for now.

Buying a new belt grinder makes sense for production quantities, but until I have the bench space for it, where to put it is the bigger issue. Almost the same issue for the Dremel drill press, except it’s more about getting to it. It’s sitting on the bench behind all the stuff that has to move somewhere else just to gain access to it. Either way there’s some bench cleanup in my very near future.

With any grinding option I’m thinking that a jig, or jigs, to hold and guide the rails would help ease the task of shaping them. The point rails need a good bit of material removed from the side that meets the stock rails. And the stock rails will need the foot removed on the point side to allow the point rail to snug up to it when that route is selected.

Grooming The Rails

Speaking of point rails, I need to modify the design to remove the ends of the ties around the throw bar and add mounting holes for the switch machine. Essentially make them hollow on the ends again, enough for the mounting brackets from the switch machine to fit and secure them with screws. Another option would be to just print the mounting bracket as part of the ties themselves.

I like the latter option better, more like prototypical headblocks, with the switch machine mounting hardware to secure it at the headblock ties’ ends, and no supports to remove. But I’m getting ahead of myself again. We’ll come back to this later. Until I have room for that new belt grinder, I can still bend the rails to the correct curvature and use the Dremel saw to cut them to length.

Up until now I’ve been using the rails from Aristo-craft 14′ and 20′ diameter curve sections with the their tie strips removed to test the fit. Time to switch to the actual rails we’ll be using. There’s still plenty of flex track rail left from our last day trip over to Pinellas Park, maybe 50′ of track, or 100′ of rail. Each rail is 10′ long, so two should be enough for the switch with some to spare.

Rough math says two 4′ long sections of track, one for each route. That’s roughly two 8′ long pieces, with maybe ~2′ leftover from each 10′ rail? The stock rails are easy to figure, and the Aristo-craft 20′ diameter curve outside rail provides an accurate template. The 14′ stock rail is more a “guestimate”, but the 20′ diameter curve inside rail is a close approximation, if not slightly too long.

Bending The Rails

Before any rail is cut, it needs bent to the correct curvature. Using enough of the Piko flex track tie strips to hold the two rails together and the rail bender, they’re coerced into the 20′ diameter curvature to start with. Again, the Aristo-craft 20′ diameter curve section provides an accurate template to compare to while bending and measure against when cutting the rail to size.

Next are the 14′ diameter rails, then the closure and point rails, and lastly the frog rails. A quick deburring with the diamond file to avoid slicing fingers open on the sharp edges and the stock rails slide in nice and easy. The 14′ diameter stock rail doesn’t seem so snug where it did previously, but somehow I managed to cut the 20′ diameter closure rail too short!

Thankfully I made the frog removable, which allows the closure rails slide right in> Then the frog is fastened in place using three M2.5 screws. From there the frog rails and the diverging route tie strips. The point rails have a single hold down which acts as the hinge, or pivot point, of those rails. Without some means to hold them in place they keep falling out. Time to work on that throw bar.

Honorable Mentions

There are a few things worth noting before diving into the next design modifications. First is the recent innovation of High Temperature PLA (HT-PLA) by PolyMaker and how it solves a key design limitation when 3D printing the curved switch parts, heat resistance. Standard PLA is no match for the Florida heat! Second is the foray into OpenSCAD.

PLA lasts only days before warping, as we found out the hard way with the Grand Hotel “skin”. We need a quick way to test this HT-PLA in the baking hot Florida sun. The quickest way there is to print something we’ve already designed, like one of those brick walls from the Downtown Marketplace storefronts. But instead of manually editing it to make it thicker, it’s time to try out OpenSCAD.

With the switch on the back burner until a decision on a grinder is made, time to look at new opportunities using the HT-PLA material. In all the discussion about FreeCAD vs. SketchUp, OpenSCAD was never mentioned. OpenSCAD is a way to programmatically design 3D models. All those tedious manual foot clamp changes could have been an easy change to a parameter in OpenSCAD.

To see more about how we tested HT-PLA and how we solved other problems for a number of mothballed projects waiting on a different solution, take a look at our cut stone retaining wall post.

A New Grinder

Getting back to that throw bar, we need the point rails and stock rails shaped to accurate place where the throw bar mounts to the point rails to provide the proper wheel flange clearance through the non selected route. How to mount the point rails is a different story. My thought is just use the Dremel drill press to drill holes in the foot of the point rails, tap, then secure with screws.

Nick has a lot of experience working with stainless steel and reminds me it requires slow speeds and heavy pressure. If anything the Dremel is high speed and low pressure. That works great for burrs and grinding stones, but not so much for drilling stainless. So much for that idea. At least I don’t have to worry about how to extricate it. The time has come for a new belt grinder.

Quick trip to Harbor Freight finds a 4″x36″ belt grinder that will fit the bill nicely. Once home, it sat in the box for a day or two before I cleared a spot for it on the corner of the bench next to the table saw parking area. Definitely made quick work of shaping those rails, starting with the point rails. The only difficulty is getting close enough to make the sharp transition the stock rail’s foot.

Finessing The Fiddly Bits

With that much said and done, the hard part is getting everything just right. The fit between the rails for the switch portion of the turnout takes some fiddling and finesse to get them finely tuned. Otherwise, the result is derailments as wheels “pick the points” and equipment ends up following both routes instead of the selected one.

Before we can even get to that point, we need a throw bar to secure the point rails together, yet space them apart by just the right amount. Again, just enough to clear the wheel flange through the non selected route. It takes quite a few iterations just to get those dimensions correct. Next thing that needs figured out is how to secure the point rails to the throw bar.

The Aristo-craft switches have a hole drilled and tapped into the web of the point rails to accept a 2mm machine screw. The screws pass through the throw bar and secure it to the the point rails. Originally I thought about doing something similar, purchasing the tap and correct drill size to do so.

But as Nick had said, using that high speed Dremel tool is a sure way to work harden the stainless steel and snap the drill bit right off. Last thing I want to do is bend more rail, cut it to size, and grind to fit a point rail all over again. Out of curiosity, I try using the 1⁄16″ hex shank drill bit by hand. Can’t go much slower than that! Pressing hard and working slowly does the trick.

Adding A Switch Machine

In no time at all both point rails are drilled. But rather than go into the web, I just drilled through the foot. There’s not enough “meat” there to rely on tapping the hole, so I used self tapping screws. Although they’re not really meant for metal, they work well enough to capture the point rails and secure them to the throw bar. Getting the placement and relief right takes a few more iterations.

Moving on to the switch machine and how to mount it. Because the switch machine itself secures the headblock ties at the proper distance apart, originally I was thinking about just modifying the design to remove the mount points from the two tie strips and incorporate both together as a single, separate unit. It would actually be two designs, one for inside throw and one for outside throw.

That way the only mounting hardware is on the switch machine itself. I opted for a compromise design that requires just a single adapter and can be “press fit” from beneath into recesses in the headblock ties. That way it can rotated to the proper orientation no matter what side the switch machine mounts to and the benefit of mounting hardware on just the switch machine itself remains.

As always, that design takes a number of iterations to get everything just right too. Using a standard Aristo-craft manual switch machine, that familiar over center “snap” action is now selecting which route through our curved turnout! Started testing clearances by running a single wheel set through each route then graduated to using an old style passenger car. It passes with flying colors!

It’s A Big Un!

If you think the 3′ long #6 and wye switches are impressive, you should see my 4′ long (~122cm) curved switch! My first rough estimate puts the frog somewhere between a #5 and #6. But it’s a curved frog, not straight, making it difficult to tell exactly what the “rise over run” values are. It does resemble the #6 frog fairly closely, so probably closer to a #6.

It’s a bit unwieldy and getting it from the workbench and out the back door to the wye was a real feat, but it fits like a glove! Perfect! Can’t wait to see whether it works or just derails everything. That depends a lot of on how well it stands up to the pups pounding on it when chasing the ball or the occasional squirrel that has the audacity to try to run along the top of the new fence.

It’s designed to be a “drop in” replacement of an Aristo-craft 20′ diameter curved section and that’s exactly how it fits. Just need to perfect those double insulated rail joiners and we’ll be all set to test the operation. At least manually. It’s going to take a bit more effort to actually get the trains running again and subject it to the true test.

Next Steps

You may ask why I don’t just buy some insulated SplitJaw clamps. At $13 plus shipping for two stainless steel insulated clamps, that gets real expensive real quick. Granted, I can get ten for $30, but compared to $300 for 60 standard clamps, $3 vs. $5 per clamp, it seems like a good deal all of a sudden. I have access to milling equipment, so I may end up making my own.

They don’t make insulated double length rail clamps, so I’ll just print the insulated part and use parts from the standard clamps to make my own. While I’m tinkering with those, I take another foray into OpenSCAD, this time to create replacement tie strips. OpenSCAD is covered in more detail in our cut stone retaining wall post. Check it out if you’re interested. Now back to the story…

A box of twenty-five Piko11″ tie strips is around $125. That’s ~$5 each! I calculated 3D printing our own at ~$2 each, but let me check my math on that one. If we can print twenty-five of them from a single 1kg spool of filament costing $25, that’s $1 each. Two spools => $2 each. etc. The slicer says 88.53g of filament, or a little over 11 per spool, so $2.22 each. On sale at $20, that’s $1.76 each.

Beyond all that, there’s more work to do to get to a final product. Once we have trains running again, we’ll see if the prototype switch can withstand the true test. Will it hold up or fall apart? What else needs done to make this a reliable part of our Barkyard RR? We’ll find out soon enough. Spoiler alert, we cover running trains in our final installment of replacing stringers.

 

Disclaimer – Not Sponsored

I should mention that the Barkyard is not sponsored by AnyCubic, PolyMaker, Elegoo, Sunlu, or any of the host of other manufacturers of 3D printers and filament or any other entities, like Harbor Freight. I don’t think they’d care much for my nicknames for them anyway, like Horrible Freight, Hazard Fraught, etc. No freebies or evaluation promotions here. This is all paid for out of pocket.

Question? Concerns? Leave A Comment!

If you’re interested in obtaining the STL files to print your own curved switch, leave us a comment and we’ll be happy to provide them to you. Also, if you have any other questions or concerns, please feel free to comment on this post. In any case, you’ll need to create a user account to do so. We don’t use any personal information for marketing or to spam you (see our privacy policy). You’ll receive a verification email. Reply to the link provided to verify your email address. It’s all automatic. No waiting on moderator approval! No spamming your inbox with useless advertisements and “Special Offers”. None of that nonsense. We do it this way to prevent bots and spammers from detracting from your experience.

More to come. Stay tuned!