New Stringers – Part III

Welcome back! Apologies for the cliff hanger from the last post, but (spoiler alert) we didn’t get trains running by Memorial Day! Had I not had a dental implant installed last week and been forbidden to do any strenuous activity last weekend, we might have had a chance. But it was not to be.

I just had my follow up visit yesterday and asked about the restricted activity. Good news! I got a pass to continue working on the stringer replacements! I had taken yesterday off anyway to make an already long Memorial Day weekend longer and give a fighting chance of making the deadline.

The new fence is in and it’s time finish up behind the shed. The mainline, switches to the sidings off the mainline, and the sidings themselves are all back in place. All the elevated sections have the track back in place as well. All that remains are the wye and ground segments from the downtown loop to behind the shed.

Reworking The 10′ Diameter Stringers

With the wood stringers it was easy enough to just use the posts to hold everything in position. These PVC stringers aren’t so forgiving. The spacer blocks want to twist, like pulling a candy wrapper on both ends to unwind it. The screws want to pull out of the PVC “end grain”, much more so than wood spacer blocks. We’ll have to glue them.

Easier said than done! Sitting it in the sun to make it “bendy” doesn’t hurt. Thankfully only the one destroyed by the hurricane, now long gone, needs replaced. The other two that remain on the side between the shed and the garage are questionable, but still functional. But before installing the new stringers, those blasted “Asparagus Ferns” have to go!

Not sure who thought these things would be a good addition to their yard, but they are absolutely annoying! Thorns sharper than roses, impossible to eliminate, short of digging them out by the roots. And that’s what was done. Not a single one remains. If one decides to pop up later, it just means there’s a root that was hiding and overlooked.

Memorial Day Weekend Progress

Between replacing the stringers and modifying the design of the new curved turnout, it’s been pretty busy this Memorial Day weekend. But there are still many more stringers to replace. After placing the new 10′ diameter curved stringer, it was apparent the posts had been pulled out behind the shed when the new fence went up. The hope was they could remain in place. No such luck.

Without them in place, more time was spent guessing where those posts actually go than painting and installing the connecting stringers. But at least that’s done now and ready for track. Once it’s repaired that is. Anyone who’s ever used Aristo-craft track and had to deal with those tiny, fumbly 2mm screws knows what a pain it is to remove them just to reseat the rail in the tie strips.

Moving on to complete the remaining straight stringers now that the stringers behind the shed are complete. The diagonal stringer that forms the Main Street crossing is already in place, so the short connector sections are next on the list. Before long they’re assembled and painted and ready to install, along with a new siding extension. So in they go.

New Solutions To Old Problems

I bought a number of rolls of High Temperature PLA (HT-PLA) filament to print my own ties for the curved switch design and replacement tie strips. Other applications include cut stone block retaining walls and brick downtown apartment storefront buildings. As usual, nineteen different projects going at once, if not nineteen thousand!

One other item of note that applies to the wye switch, the curved switch, and the HT-PLA. Previously I had designed and printed insulated replacement parts for the SplitJaw™ clamps on the diverging routes of the wye using standard PLA.  It quickly became apparent that PLA is no match for the Florida sun! Another one of those found out the hard way items.

Essentially the PLA slowly deformed in the heat until the track joints simply gave out and popped open with all the stress those curved wye leg rails are under. Hopefully this recent improvement of HT-PLA will fit the bill. But before using HT-PLA in earnest, it has to withstand the test of the Florida sun and heat. We’ll find out soon enough.

Surprise! Surprise!

Not much surprises me anymore, but I am absolutely amazed at the performance of this HT-PLA! The first test was printing and annealing 8″ long brick walls, fairly thin at ⅛” thick, then leaning them over the 4″ tall half height concrete blocks that make up the station platform and leaving them out in the sun all day. They remained straight and tall, no bending, sagging, or warping!

Next was 4″x7″ black cut stone block retaining walls. Same outcome! As expected, being black, they got hot. Really hot. Like nearly 150°F! I got out the infrared thermometer to measure. It and most of the turf were ~145°F! The darker green turf was even hotter at ~155°F! I don’t know how Rocket can stand to walk on it, let alone lay down on it, but I couldn’t get him to move from there!

Those cut stone retaining walls were entirely another project. I’ll have a post about them to link to soon. Let’s just say it took a number of different false starts just to get something that could be 3D printed. But after a few design iterations, it’s now a viable part of the station siding facelift. Let’s just say I ordered a LOT more spools of HT-PLA filament just for them. Stay tuned for more details.

Progress Continues

Fast forward a few weeks and it’s time to install the wye trackage, starting with the wye switch. The mainline switch and sidings have been installed for nearly a month now. Time to get the track and as much of the wye installed as possible, in anticipation of the new curved switch prototype.

The curved switch design began in earnest the beginning of May, and has slowly evolved into its current incarnation, using HT-PLA for the ties, frog, and throw bar. Even an adapter for the standard Aristo-craft switch machine. There’s even a preliminary version of a servo driven switch machine on the drawing board, now printed using HT-PLA. But that’s yet another project for another day.

The most difficult part of refurbishing the wye is already done, with the exception of figuring out which of the many curved flexible track sections are the two that go there. Actually, a number of them will fit, just not sure which are the right ones. But I’m getting ahead of myself again. Time to fit the wye switch in place. The curves will follow.

While We’re At It

While I was going through the rest of the flexible track sections looking for the wye pieces, I decided to figure out where the rest of them belong too. The original thought was to just get the downtown loop operational to be able to continuously run trains. That’s still a ways off, but the 4th of July will be here before we know it. We’re not missing that deadline!

It took a number of iterations to figure it all out, just like the wye legs did. For now the track’s all just laying on the ground approximately where it goes, waiting for another time to work on it. The remaining parts of the wye need finished before any of it can be connected, so it will have to wait until that’s done first. Then the drudgery of removing what remains of the rotted stringers begins.

Again, that’s not on the schedule. Not yet anyway. Just getting the continuous loop up and running is the goal, and it’s almost a reality. Just a few more things until the first test run! But those things are going to take another weekend, if not two, putting us well into June.

About That Wye…

Setting and levelling the stringers for the legs of the wye takes the entire weekend, but is well worth the effort. More excavation is required, but it adds more dirt to build up the embankment with. Enough dirt that the turf needs pulled up to allow contouring the additional overburden. But I’m getting ahead of myself again.

The turf is two long sections that are way too heavy to lift all at once, covered in a couple inches of leaves and acorns and gravel and already full of trapped dirt. You name it, it’s covered in it. All of it is slowly shoveled off and added to the base of the elevated track section just beyond using just that small, hand sized garden spade. Building up that embankment is slow going for sure.

Beyond that, the turf needs cut from beneath the long straight leg just to extricate it and excavate even more dirt to set those stringers in place. That hadn’t been part of the original plan. But because the turf’s essentially trapped beneath the stringers, it has to be done. Slicing the turf along the plastic edging that defines both sides of the right of way frees it up.

Can’t recall why it was done that way the first time around with just access openings in the turf for the posts. Perhaps the thought was it would reduce the likelihood of rot. The evidence proved otherwise. Perhaps it was more expedient. Certainly paying the time penalty now for that decision in the past.

Earth Moving

Thankfully it’s in a number of pieces, but even those are heavy. They are so heavy with trapped dirt I can barely lift one at all. The trick is to lift by an end or corner and shake the dirt loose into a pile that can then be easily moved where desired. Slowly but surely the dirt is shaken out of the turf, little by little, until the entire length is now laying upside down on top of the embankment.

More dirt needs moved and contoured with the flat shovel to shape the embankment. Posts need persuaded into place using the sledge hammer. Wiring needs rerouted and buried along the newly created “trenches” the stringers now sit in. Last but not least is cutting the remaining turf to fit the new topology. It’s exhausting work, in the midst of a heat advisory, but well worth the effort.

The embankment finally looks like an embankment. The wye finally looks like a wye.  And best of all, it looks like it’s meant to be that way. Not an afterthought. Not a pile of dirt under the raised track section. Ann was not very happy about all that dirt at first, worried about slipping on it and falling while stepping over the tracks. But now she says it looks great, like it’s supposed to be there.

Unveiling The Curved Switch

Fast forward another weekend and it’s finally time to test out the prototype curved switch. At four feet long (~122cm), it’s a bit unwieldy. Getting it from the workbench and out the back door to the wye was a real feat, but it fits like a glove! Perfect! Can’t wait to see whether it works or just derails everything.

For now, just the 14′ diameter diverging route is connected to the North curved leg of the wye, but the 20′ diameter route provides the starting point for laying down the straight leg of the wye. The track for the other side of the curved switch can now be put back in place too.

That much needs to be completed to be able to lay the rest of the ground level track up to and around the curves behind the shed. Hopefully it’s apparent why starting from that mainline switch and working the wye and the rest of the track from there is mandatory.

Growing Pains

We’re using standard SplitJaw™ rail clamps on the mainline side of the wye switch and our homebrew “double” insulated clamps on both the diverging routes.  In this case, double insulated isn’t meant in the sense of power tools, but rather a double length rail clamp, using four screws where the standard clamps use just two. Lots of growing pains there.

Every time I look, the dogs have once again pulled the joints loose or broken the clamps altogether! The prototype didn’t allow them to tighten all the way. Subsequent versions using annealed HT-PLA just didn’t have the strength. Many design iterations later they finally survive the constant pounding of fetching the ball and chasing the squirrels. Double insulated and now double thick!

And now that the rail clamps keep everything together, all the track moves together… Right off the stringers! This is going to take more than wire ties to keep the track aligned and remain on top of the stringers. Going to have to think about that one. First thought is something like the deck sections that hold the track in place for the station siding. We’ll revisit that later.

Growing Trackage

The curved switch is designed to replace a full 14′ diameter section (22.5°) plus an additional 1⁄3 section (7.5° – grand total of 30°). If geometry and angles aren’t your thing, it takes sixteen of the 14′ and 20′ diameter sections to complete a circle. It only takes twelve of the 10′ diameter sections (each section is 30°). The curved leg of the wye is a single piece of flex track just the right length.

Long story short, there are three remaining 14′ sections to place after the switch points bringing us to point due East. Those 14′ sections connect to two 20′ diameter which turn us Southeast. Those connect to two 5′ long straight sections, running diagonally across Main Street. A short connector section joins to another set of two 20′ diameter sections that bring us back to due East.

From there a 2′ straight section connects to three 10′ diameter sections, bringing us due North behind the shed. The mainline also crosses Main Street, but perpendicularly. It then connects to another set of three 10′ diameter sections, again bringing us due North behind the shed.

All Coming Together

It’s all coming together rather nicely. The only missing trackage is the 10′ diameter curves and the straight sections to connect them behind the shed (and all of the lower loop around the deck). I didn’t think I had enough of those 10′ diameter sections left that could be repaired, but it appears I was wrong. There were enough for all but one quarter circle, made up with flex track.

The remaining straight sections behind the shed will need cut to fit. Time to break out the tape measure, Dremel saw, and diamond files. Might also need a few new tie strips to hold the rails in place. My skills with the Dremel saw leave much to be desired. Nothing a diamond file won’t fix, but need to start thinking about designing and 3D printing a “chop saw” jig for making precise cuts.

That completes the entire continuous loop of track. It’s been a long time when we could last say that. With that much done, it’s time to turn to the wiring. But it’s already getting late on yet another Sunday out in the heat advisory weather. The wiring will have to wait for next weekend, along with running trains. As much as I’d like to test the track, patience is prudent.

At this point. it’s almost like starting over with the wiring anyway. Thankfully all the fuse positions and most of the cables are labelled, albeit upside down on the fuse box and weather faded sharpie on the cables. The three new wye cables aren’t labelled at all! Need to break out the multimeter and start testing. Next weekend.

Question? Concerns? Leave A Comment!

If you have any questions or concerns, please feel free to comment on this post. In any case, you’ll need to create a user account to do so. We don’t use any personal information for marketing or to spam you (see our privacy policy). You’ll receive a verification email. Reply to the link provided to verify your email address. It’s all automatic. No waiting on moderator approval! No spamming your inbox with useless advertisements and “Special Offers”. None of that nonsense. We do it this way to prevent bots and spammers from detracting from your experience.

More to come. Stay tuned for Running Trains!

 

Making Realistic Cut Stone Retaining Walls

Welcome back! This is the story about achieving our long time goal of 3D printing realistic cut stone blocks. For the longest time it was out of reach, mainly because of my limited abilities, coupled with the limitations of the tools I’m using to capture the designs. But renewing the search to find new approaches to solve the design problems finally paid off recently!

Before we dive right in there’s some history we need to cover. It may seem like the long way around, but some backstory helps describe the problems looking for solutions, and the journey to find them. This all started long ago when we decided to use the concrete patch casting method for the walls of our Downtown Marketplace buildings.

We were off to a good start, learning from the mistakes of the first casting, and made two more. Painted, weathered, and detailed with 3D printed windows, doors, and display cases, they were impressive. We used mortar to attach them to concrete blocks for added strength against the Barkyard’s marauding German Shepherd population. Then other priorities stole us away.

I wanted to give proper credit where it’s due, but I’m sad to say the original site (rrstoneworks.com) I used as a reference for this technique is no longer online. They sold plastic pattern sheets and actually sliced real stones into what they called “Stone Sticks”. I have two boxes of them, with no way to get anymore of them. Need to check the “Wayback Machine” for anything useful…

It didn’t take long to realize the 3D printed PLA parts weren’t up to the task. The final nail in the coffin was the grand experiment, the Grand Hotel, also 3D printed from PLA. It lasted only days before it warped, got brittle, and fell apart. Another failure. The only thing durable enough to last over the years were castings. We detailed what it took to make that happen in this old post.

A Bit Of History

Fast forward a bit to casting retainer walls for the track to climb the grade it makes along the back fence and around the corners. We’ve already moved a LOT of dirt to create the embankments with the proper slope that sits beneath the tracks to support the retaining walls, pretty much following prototypical practice.

Struggling with designing casting molds for weeks, then months, the final version is still lacking years later. It lacks a definitive means of supporting the walls and connecting them together in a rugged fashion. It lacks a mechanism for adding on new segments to previously placed ones. Most bothersome is the lack of detail in the large, cut stone blocks that make up the wall.

The idea was to pour concrete into forms that would capture the castings and hold them in place while the concrete hardened then remove the forms. The design progressed about this far, printing mockups, and assembling them to help visualize what we’d encounter when doing this for real with mixed concrete ready to pour, detailed in this post. It was overwhelming. The design was tabled.

More Backstory

Fast forward a bit more to casting concrete roadbed bricks. Another learning process. Another shelved approach. The original approach was to form and pour in place, then “screed” the ballast profile into the wet concrete, like those concrete curbing machines do. That proved to be a lost cause, perhaps because the mix wasn’t wet enough, perhaps because I’m a novice and not a Mason.

The next iteration was to create a long mold to cast individual “bricks” from the concrete. Screeding the top flat was much easier than trying to form a profile shape, but setting up the mold with all the pieces in place then cleaning up the mold afterward was tedious and time consuming. The mess of pouring concrete and the strenuous effort of mixing it adds up to more effort than reward.

Another drawback to any sort of casting is the amount of time involved, beyond the preparation and effort. It’s a series of “hurry up and wait” events that have to occur within a fairly strict timeframe. Once mixed, the pour has to occur quickly afterward. Then wait at least a day but not much more than that before removing the green castings from the molds. Time to find another way.

New Solutions To Old Problems

Previously I had designed and printed insulated sections for the SplitJaw™ clamps on the diverging routes of the wye. It quickly became apparent that PLA is no match for the Florida heat! Essentially the plastic slowly deformed until it simply gave out and the joints popped open with all the stress those curved legs of the wye were under. Another found out the hard way item.

Even PETG struggles with the heat. Nick was having similar issues with 3D printed parts for his “under hood” automotive applications, but he found a solution, High Temperature PLA (HT-PLA). He printed a set of coil mounts with it to test how well it stands up to the high temperatures in the engine compartment. The parts need “annealed” first though to give them their heat resistance.

As a test, he annealed one mount but not the other, then installed them on the engine. One melted. One did not. Needless to say annealed HT-PLA passed the test. He swapped out the melted one with another annealed one and they’re still going strong. I bought a roll of black HT-PLA filament a while back to see if this recent innovation will fit the bill for our needs too.

New Opportunities For Old Projects

The bench space issue in the garage has delayed further casting, waiting for the bench to be cleared off, literally for years now. The reason for castings is twofold. First is durability when faced with constant pounding from three German Shepherds. The second is resistance to the brutal Florida heat and environmental challenges in general. Concrete holds up better than wood or PLA.

PLA lasts only days before warping. We found out the hard way with the Grand Hotel “skin”. We need a quick way to test this HT-PLA in the baking hot Florida sun. The quickest way there is to print something we’ve already designed, like one of those brick walls from the Downtown Marketplace stores. But instead of manually editing it to make it thicker, it’s time to try out OpenSCAD.

What better test for something that’s an exhaustively “manual intervention required” task than laying out a brick pattern? In a little over an hour the OpenSCAD model is rendered, exported as STL, and printing! While that’s printing, it’s time to learn even more about OpenSCAD and make the hard coded preliminary model more parametric.

Parameters like how tall and wide is the wall? How many windows? What scale? Brick dimension? Adding those features took a little more than a day to resolve, but now it’s totally configurable and can even create Downtown Marketplace storefronts! Just flip the switches and change the values and render another model, then export the STL and print!

Test Time

Before going any further with the grand experiment of HT-PLA, we need to test whether it will perform as required. I expect it to perform as well as it did for Nick. The first brick walls were printed using red HT-PLA. They were then annealed at 100°C (212°F) for 30 minutes as recommended by PolyMaker, the filament manufacturer, and allowed to cool back down slowly in the oven.

Glad I saved the “Easy Bake” toaster oven from the scrap heap. The only thing wrong with it is the broken handle, quite the nuisance when dealing with that hot glass door. It still works fine though. And it’s old school! Everything’s set using dials, including one of those timers that winds up and slowly ticks away, counting down to DING! It’s done. No modern computer crap to fail.

Once annealed, I set the walls out in the sun all afternoon, standing against the half high concrete blocks, where they can bend at about the halfway point under their own weight if they’re going to. Thinking the oven was plugged in when it wasn’t, the first brick panel didn’t get annealed, creating a side by side comparison test similar to Nick’s. That panel warped slightly into a convex shape.

But the rest of them passed the test with flying colors! WOOT! They’re only ⅛” thick and no deflection whatsoever! No warping. No distortion. No discernable changes at all. Nothing. Absolutely amazing! I tried re-annealing the warped one using a weight to try to flatten it back out, but it just warped into a concave shape this time. Oh well, at least now we know what to expect.

Riding The Wave Of Success

It’s the convergence of multiple successes coupled with a potential solution to the heat resistance problem that prompts pulling the cut stone retaining wall design out of mothballs. A quick search online reveals a post on the Model Railroad Hobbyist forum by Glenn Butcher about his solution to the exact thing I’m looking to accomplish! What are the odds?

At first glance it’s way too overcomplicated as a quick solution, but then I see that Glenn has already created 20 textured stone STL files, and in OpenSCAD no less!. Now that’s the ticket! Without getting way too technical, he generated “height maps” to use as the textures using a technique the makers of Star Wars used to generate realistic, computer generated terrain.

In fact, the approach is captured in an publicly available library, libnoise, that anyone can use in their own programs. That’s exactly what Glenn did then shared his work, noisetool, online. Sounds good, right? The drawback is those height map files for OpenSCAD are tens of thousands of lines long. Each. Now put 20 of them in one program! Good luck scrolling through something that big!

Making It Work

I know, engineers, right? I thought I over-engineered things, but Glenn takes it to a whole new level. That’s a good thing! Each of these textures is meant as a 3″ x 6″ HO scale wall, but our cut stone blocks are ½”x1″, a 6:1 scaling factor. If we want one out of six in two directions, 6 x 6 = 36, and we only want one of them. We could throw out 35 of 36 values and still have plenty of detail.

In an attempt to work around pasting all those huge files into OpenSCAD and simply import a series of 20 files that captured each of those height maps as solid models I used an online tool that converts STL to OpenSCAD files to be able to import those 20 STL files as modules I could include in OpenSCAD and then arrange them programmatically.

I get it all working up until I try to actually render it to export the STL and get a “Thrown Together” error for every stone! Not sure what that means or how to fix it. A quick search says I should try a development version newer than the 2021 release version. I don’t have the time to throw at getting a development version of the program working. This was supposed to be a quick win.

Next!

Well that was a LOT of wasted time for absolutely no reward! Time to get it working in SketchUp. I imported the series of 20 STL files that captured each of those height maps, one at a time, into FreeCAD. Once there, I created a mesh from the STL, optimized the mesh, and then created a solid from the optimized mesh and exported them as .dae design file models SketchUp understands.

Alright, I promised I wouldn’t get too technical, but it’s worth noting how I created the models. Rather than write a program to sift through all that data and throw out what we don’t need, I just pulled the solid models exported from FreeCAD into SketchUp. From there they’re scaled and the stones manually arranged into our familiar 4″ x 7″ retaining wall segments.

Next HT-PLA test, black cut stone retaining walls. If anything doesn’t stand up to baking in the hot Florida sun, it’s black anything. Anyone who has a black car interior knows how scalding hot those surfaces get after baking in the sun all day. Can’t even touch the steering wheel for minutes, even after the A/C is blowing cold on it, and even then you wish you had gloves.

Adding Realism

It takes some time to get all those stone models imported and resized to fit our existing retaining wall dimensions. It’s soon apparent there’s WAY TOO MUCH DETAIL! What used to be snappy response times are now so sluggish I’m wondering if I actually pressed the key or clicked the mouse. In any case, I lay out a pattern of blank, mock stones then replace them with the imported ones.

One by one I substitute the textured stones until I’ve used all 20 of them, the first three courses out of eight. The next three courses I start at the beginning again, but flip them along their green (Y) axis, from left to right, effectively making them a mirror image of the originals. The last two courses use a similar approach, except this time flip along the red (X) axis, mirrored from top to bottom.

That leaves the “half” blocks at the end of the staggered courses. I chose a handful of stones that look the flattest, with the least amount of detail, because sizing them to half their length will stack twice as much detail in the same amount of space. It works out well and the mock half blocks are replaced with the actual stone models in a similar fashion to the full blocks.

There! Now we have a “flat” wall with realistically textured cut stone blocks that we can test with. Well, once the STL is exported, sliced and 3D printed we do. First it goes into the Easy Bake oven to anneal. Then it’s punished by the Florida furnace. Fingers crossed this will hold up to the heat. The flat wall passes with flying colors! It sat out all day, then overnight, and again all the next day.

Testing While Adding More Realism

Meanwhile I’m working on making the flat wall sloped to match prototypical construction. When I say “flat” I mean the blocks are stacked directly on top of the course below, with no lean either way. The prototype calls for an inward lean to account for the increasing forces exerted by more and more dirt the deeper down it goes. The sloped profile is more realistic than the original flat version.

Each new iteration of the evolving design gets printed and added as a new test subject. All the black test subjects have been baking in the sun all week with no discernable changes. Absolutely awesome! That means using the HT-PLA for tie strips is a possibility too! Time to try printing the switch ties for our new curved switch with it.

Another practical use is rebuilding the Downtown marketplace using HT-PLA instead of castings. It may not save much time over castings, each 5″x8″ wall segment takes hours to print, but it’s far less messy! And it certainly doesn’t take as much prep and cleanup time as casting. But we’ll save all that for another post.

Some Caveats

There’s something to be said for getting it right the first time. Something that seldom happens. I have a bin full of useless prototypes that didn’t make the cut. May as well get used to burning through at least a 1kg spool of filament prototyping a design to get to the production version. Or should I say a production version? There’s always that one last tweak to add…

Each part of this design has evolved to suit the requirements of the station siding, and now by extension, the ever evolving station platform. But I’m getting ahead of myself again. The initial design elements are primarily the walls and pillars that join them together, the track deck and capstones, and the underlying frame that ties everything together around the stringers.

Originally the walls were glued to the pillars. More like solvent welded, similar to using plastic model cement. But it quickly becomes obvious after about four wall panels that a wall 10′ long can’t easily be moved all together all at once without breaking apart. Time to rethink the design. So now everything is modular, held together using M2.5 stainless steel socket head cap screw hardware.

Modular Design

That four wall panel section is still sitting on the office book cases. I just can’t bring myself to throw it away yet. Why four panels? Because that’s the magic number of roughly 8″ (~20cm) sections it takes to make a complete 10′ diameter track section. The pillars are designed to angle each wall panel from the last by 7.5°. Four gives a total of 30°, the extent of a 10′ diameter curved track section.

Two M2.5x6mm screws hold the pillar to each wall panel, a set for each panel on either side of the pillar. The transition to tangent track and remaining walls have another pillar design that has no included angle so the wall panels remain straight and parallel to one another. There is one exception for the inside transition from 10′ diameter, mainly to accommodate track deck mounting.

The track used to sit directly on top of the stringers, but now it sits in a “trough” in the track deck, as deep as the ties are tall. The “floor” of the trough the ties sit in is ⅛” (~3mm) thick and now sits directly on top of the stringers. The track is not mounted down to the track deck, but rather left free to “float” in the trough, and the track deck itself mounts to the underlying frame.

Keeping Things Where They Belong

The frame surrounds the stringer, the main reference for track placement, holding things together and where they belong relative to the stringer. The frame is a three piece design. Two tall sections that mount to the back of each opposing wall pillar using two M2.5x8mm screws. The third “Twist Lock” piece pulls the opposing mounts together and locks the assembly around the stringer.

Leaning the twist lock back at an angle allows the set of “hooks” at the bottom to catch and hold just inside those two mounts, then by twisting it up into position, it locks everything together, including the wall pillars. The twist lock section is secured to the mounts using two M2.5x10mm screws from the top, mainly because that’s about the only access left once everything’s assembled.

The track deck itself mounts to the underlying frame using four M2.5x10mm screws, covering and blocking access to those two screws securing the frame pieces together at either end of the deck. The socket heads are recessed into the raised portions of the deck on either side of the track that forms the trough. Eventually they will be concealed by a fence, roof supports, or some other cover.

The capstone strips are secured to the deck from beneath using M2.5x16mm screws. Once the deck is mounted to the frame, they are no longer accessible. The single, larger pillar capstones can be held in place by simply inserting their built in tabs into the slots in the underside of the deck capstones. They can also be secured using button head cap screws, but it generally isn’t necessary.

New Challenges

With enough 10′ diameter sections in place to account for the surrounding grade increasing to meet the track level and the kinks in the transition to tangent track hammered out, it’s time to think about the station platform and how to connect it to what we have so far.  More specifically, how to incorporate the old station platform 4″x8″x16″ half height concrete blocks into the new design.

The whole sad story about how nothing’s left of the original station platform was left out of the earlier history lesson. The abridged version is there used to be raised bed planters along the entire length of the patio. Those blocks sat between them and the track stringers, with a roof of sorts from the planters above acting as a covered station platform.

The planters were removed long ago, leaving just those blocks along the station siding track. Because the track sits roughly 4″ off the ground, any kind of platform would need a good bit of support or dirt fill beneath to hold up to the constant pounding from the pups. We already have all those blocks just sitting there anyway, so why not incorporate them into the design?

Transitioning From Curved To Tangent

Before we can use those half blocks, we have to transition from the curved approach to tangent (straight) that will become the station track alongside the platform. This is the exception for the inside transition described above. The exception it refers to is where the curve track deck meets the tangent track deck.

Originally the thought was to have a transition track deck and transition pillars. Partway into that design it was discovered that not only would it take one transition track deck, it would need two of them and both of them would be different! Basically one to go from 7.5° apart to 3.75° apart, and then from 3.75° to straight and corresponding pillars to match. But that didn’t make sense.

The current design simply reuses the curved and tangent track decks along with a regular 7.5° pillar outside and the new transition pillar inside. The inside transition pillar has a 7.5° angle too, but the stones are offset from the middle of the angle to account for the track deck mounting locations. I feel like I’m waving my hands again, but this gets us from curved to straight using fewer parts.

By shifting the mounting points on the inside transition pillar to accommodate the standard track decks, it eliminates the need for at least three or more additional, specialized parts, only useful in this one situation. Too bad I didn’t think of it before designing a number of those specialized parts first and then having to toss them out after wasting all that effort.

Transitioning To A Platform

So now that we’ve transitioned from curved to straight, before we can use those half blocks, we still have to transition from the current approach track with retaining walls on either side to a platform with a retaining wall on one side and a station track on the other, the station track with its own retaining wall on the other side, continued from that side of the approach track.

Hopefully the “see through” panels give a better view of how all these 3D printed parts come together to give the illusion of a believable scale model. For me, seeing them slowly come together and become what I’ve always dreamed of seeing is more than satisfying. It truly is a dream come true. The black and gray colors aren’t very realistic, but until the design is finished, it’s good enough.

The design must account for the inside wall changing direction, in this case perpendicular to it. In order to widen the footprint and conceal the half blocks with something that looks like a station platform, we need a different inside transition pillar, plus an additional outside transition pillar to redirect the wall back to the original approach wall direction along the side of the platform.

Unfortunately, because of the dimensions of the half block in that direction, we can’t use the standard 4″x7″ wall connected to all the other pillars. Altogether they add up to 8″ total, too short to wrap around the 7⅝” width of the block. We’ll need a 4″x8″ wall to allow just enough clearance for that block width.

Expanding The Design

So now instead of two opposing wall pillars separated by the width of the track deck one of those frame mounts will now connect a “hidden wall” section to the opposing cut stone wall. These hidden wall sections will mimic the cut stone wall dimensions along with their own pillars. They connect to a widely separated cut stone wall pillar on the other side of the block every 16″.

Because the block is actually only 15⅝” long, that leaves just ⅜” to work with. The connecting frames between the hidden walls and far cut stone walls are only ¼” thick, leaving barely enough room to spare. It’s a tight, snug fit, but it anchors everything and supports the platform sections. Each section is still only 8″ wide because of 3D printing build volume and “Easy Bake” oven limitations.

Two platform sections are joined together and fitted 16″ at a time. A “stub” mount for the platform sections is used in place of a connecting frame section where the block length is in the way. This ensures the hidden and far cut stone walls are still rigidly secured together even where a connecting frame member can’t be placed.

Adding The Station Platform

The track deck still mounts to the twist lock frame, but now only one of the capstone strips is needed for the side opposite the platform. The platform design itself takes some thought about how to make a believable scale model that doesn’t have obvious separation “cracks” every 8″.  Why not a brick herringbone pattern framed by what appears to be stone blocks?

OpenSCAD to the rescue again! It takes a bit longer than expected to perfect the design, but it’s a believable herringbone pattern, centered about all four sides. It even has mounting holes to attach a support frame that the framing stone block strips will also attach to. Those stone block strip designs are captured in SketchUp along with an imported version of the brick herringbone piece.

To facilitate the modular design concept for adding new sections, the edge of the new platform section will simply slide in beneath a previously mounted section without need for mounting screws. If anything, loosening the existing mounting screws that hold the previous section may be necessary. Then both the old and new platform sections can be tightened down together.

One last “transition” design item is necessary for the first platform section along that 4″x8″ wall. There is absolutely no room for any mounting hardware to fasten the edge of the platform to the wall beneath. The half block butts up against the back of the wall to fit everything in the limited 16″ space. Instead, a set of tabs on the first platform subframe slides into slots on the transition pillars.

Assemble, Rinse, Repeat

After that first transition section from the approach configuration to the platform configuration, it’s simply a matter of adding on another 16″ platform section to the previous. Expanding from first platform section to the third doesn’t happen happen overnight, but it doesn’t take long since I’m printing most of the parts while redesigning the ones that aren’t working as expected.

The only limiting factor on the platform expansion is how long it takes to 3D print all the parts, anneal, paint, and assemble them into the next 16″ section. It takes a lot of parts! Four each retaining walls and pillars, two each hidden walls and pillars, twist lock frames, hidden frames, platform decks, platform subframes, deck border stone sets, track decks, and track deck capstones.

I’ve tried to capture the estimated print times of all the parts when slicing them. Let’s see how well I did and whether I can add them all up for a rough estimate of print time. Add at least another hour to anneal each print, although the last part printed can be annealed while the next is printing. Then add painting the annealed parts and assembly time. It all adds up. But progress is progress.

Color Considerations

Our color palette in HT-PLA is fairly limited, even more so than PLA. Just the basic colors. While the capstones could have been printed in white, the single ACE cabinet only has four slots it and would mean having to constantly swap between white and one of the other four colors, namely black, brown, gray, and red.

Gray was chosen with the idea that the red is too bright for bricks and would need painted brick red anyway. The track deck and capstones can be painted concrete and light stone colors. The black cut stone walls don’t need any paint, but should probably have some sort of UV protection painting the other parts offers, and perhaps a wash with a lighter color to bring out the details.

After an extensive Google search for matches to the Model Master “Aged Concrete” color from my HO scale days, satin Dover White and satin Ivory are chosen for the concrete and light stone colors. At first, they look like they’re same color, but later spray paint batches aren’t as close. Natural variations in stone colors? Plausible explanation if anyone asks. LOL.

Brick red is brick red. Alright, there are variations to be sure. I even made brick color selectable for OpenSCAD, brick red or creme (beige). I’ve seen many modelers design and print painting masks to expose “random” bricks and paint them slightly different colors to mimic the natural color variations. I know I’m a rivet counter, but I haven’t made it to that level of obsession to detail (yet).

What’s Left?

The station platform is slowly expanding. The original platform was 16′ long. Now it extends beyond the end of the patio, so approaching 20′ maybe? So far we’re about half way done, right at the end of that first 10′ stretch of flex track. We can add another 16″ section every couple of days in production mode, pretty much 3D printing parts 24/7.

I’ll wake up in the middle of the night and kick off another if the previous print’s finished. Sometimes I’m a sound sleeper though. But it only delays the inevitable, kicking off of the next print once I’m able to. So far I’ve only screwed up twice trying to go faster than I should have.

First was forgetting to put the PEI sheet back in the printer and frantically killing the print before it could cause more damage. I’m missing a small chunk of the magnetic material that holds the PEI sheet to the build plate after that little fubar. Kicking off another print while the previous one was still sitting in there on the PEI sheet was another. “Why’s it making that clunking noise? OH SHIT!”

I can laugh about it now, but it certainly wasn’t all that funny at the time! Getting back to what’s next, the end panel of the platform still needs designed. Similar to the transition to platform configuration, now we get to the terminate the platform and need to finish it off with walls and pillars that connect the retaining wall together. We won’t have the luxury of tabs and slots this time!

Future Reference

Observations for future reference – overlaying two stone textures atop one another gives a much more realistic looking stone face, but not sure how to “add them together” in a usable fashion. Maybe someday. This is mainly a note to my future self when revisiting the stone texture design. It’s strange that when I rendered the imported stone modules this time it didn’t error out. WTF?

I’ll update this post periodically with progress toward completing the station platform. For now, I just want to get this posted. I’ve been so busy doing so many things it seems impossible to both do and post. I haven’t looked at editing a video in months. Everything takes time and right now the focus is getting the trains running and restoring the previous “luster and glory” of the Barkyard RR.

I have to say I’m pleased as punch with the outcome of this project! It’s been a long time getting here, but it’s worth the wait for the result! All the projects I put on hold are slowly coming out of mothballs. All the things I’ve put off for so long are finally coming to fruition.

In the past I worried about prioritizing things that needed done first. Anymore, I just do what’s staring me in the face, then ask myself, “What’s next?” and just do it. I kind of have to since I do things like buy a bunch of clearance Aristo-craft stuff that’s not in the best condition, then have to design and 3D print replacements for all the broken and missing parts while juggling 19 other projects.

So far so good, but that’s another story.

 

Disclaimer – Not Sponsored

I should mention that the Barkyard is not sponsored by AnyCubic, PolyMaker, Elegoo, Sunlu, or any of the host of other manufacturers of 3D printers and filament or any other entities, like Harbor Freight. I don’t think they’d care much for my nicknames for them anyway, like Horrible Freight, Hazard Fraught, etc. No freebies or evaluation promotions here. This is all paid for out of pocket.

 

Question? Concerns? Leave A Comment!

If you’re interested in obtaining the STL files to print your own block walls, leave us a comment and we’ll be happy to provide them to you. Also, if you have any other questions or concerns, please feel free to comment on this post. In any case, you’ll need to create a user account to do so. We don’t use any personal information for marketing or to spam you (see our privacy policy). You’ll receive a verification email. Reply to the link provided to verify your email address. It’s all automatic. No waiting on moderator approval! No spamming your inbox with useless advertisements and “Special Offers”. None of that nonsense. We do it this way to prevent bots and spammers from detracting from your experience.

More to come. Stay tuned!

 

Making A Curved Turnout – Part II

Welcome back! This is the second part of the curved turnout series. If you haven’t seen the original post yet, you may want to start there first. A good part of this discussion relies on topics covered there already. So where did we leave off? That’s right, the new spool of filament wasn’t the best. The brittle nature of the filament is causing problems with prototype fitment and development.

Its brittleness coupled with a lack of complete support removal is a sure way to snap the foot clamps right off when attempting to test fit the rail. So one more refinement will be to back them off another 10 thousandths as well as raise them all by 10 thousandths. It’s also a vote to just reprint those other ties strips using the other design refinements so far.

But that’s not as easy as changing one model to fix all of them like it was with the diverging route ties. Every one of those remaining switch ties is unique. There are 48 of them altogether. This is where SCAD or other parametric CAD applications shine. Need to nudge everything in the same direction? Simply update that parameter and rebuild the model.

For example, to increase the distance between the tie and foot clamp, it’s a simple change to increase that parameter and rebuild. Not so much with SketchUp. It’s all tedious, time consuming manual effort per clamp per tie. I suppose I could have used a component to model the rail foot clamps, where changing it once would affect all instances, but it wouldn’t account for other factors.

Why Not FreeCAD?

As much as I’d like to put this design in FreeCAD, I keep falling into the speed trap. The speed of implementation trap that is. I already know how to do just about everything in SketchUp and how to workaround things it doesn’t handle gracefully. For me with FreeCAD, it’s at least a Google search, if not another lengthy tutorial video just to learn the basics.

There may come a day I don’t feel the time crunch, but today is not that day. I need to put this new printer through its paces to verify everything is working, and working the way it should. Like most warranties, they’re for a limited time only, plus I want to get rid of the shipping box I’ve been saving in case it needs sent back. The sooner the better.

What new printer? It’s an AnyCubic Kobra S1 Max Combo. It arrived about a month ago and I’ve been waiting for it to get here since I ordered it around Thanksgiving last year (2025). It has a build volume of 350mm x 350mm x 350mm (13.77″ x 13.77″ x 13.77″) and can print up to four colors with the single ACE cabinet version I bought. With more ACE cabinets, it can print up to 16 colors.

All that being said, now I’m paying the time penalty for using SketchUp, which means having to revisit every single one of those rail foot clamps, adjusting them one by one, for every tie. I marked the ones I had to adjust from the initial 17′ diameter tie placement and stretched to fit the 14′ and 20′ diameters. Thankfully I also marked the ones I had to adjust for interference.

Moving Forward

Now the question is whether to just save the current version as a prototype fallback and make the changes to a new version or press ahead blindly. The latter is what I got without even thinking about it. Now I’ll find myself unable to rewind to a previous version later. SketchUp is unforgiving when backtracking to a mistake made many operations ago.

On the plus side, reprinting all those tie strips means I don’t have to finish cleaning up all the rest of those supports! There are few more things I’d like address while I’m at it, like how to mount the frog to the tie strip. The screw placement and openings for the mounting hardware need laid out. If I print things in the same order, I’ll have time for that while the others print.

Another thing I need to look at is using spiral vs. rectilinear top surface texture when slicing to 3D print. The former leaves a pattern that resembles wood grain and the spike head details are visible, but the “diagonal corner” is unrealistic. The latter is smoother, but those spike details are missing. There may be a way to tell the slicer not to rotate 45°. If there is, I certainly haven’t found it (yet).

This will sound like nonsense to folks who aren’t familiar with 3D printing, slicing in particular. Hopefully this isn’t too basic, but 3D printers do their work a layer at a time, building each successive layer on top of the previous one. The slicer effectively slices a 3D model into layers, hence the name slicer. It tells the printer what each layer looks like and how to print them using GCode format.

The Slow Grind Of Rework

Reworking the rest of those tie designs is a chore. A chore I’m not looking forward to. Hours and hours of zooming in on each an every foot clamp on each and every tie for days on end. Thankfully my motivation hasn’t failed me, printing the fruits of my labor while pressing on to finish the next section. Unfortunately it’s finished printing the previous section long before the next is ready.

I knock off “early” the first night at 11:00 PM, knowing the guys will be here bright and early the next morning to put up the new fence around the Barkyard. But that’s a different story for another time. By the end of the second day I finally have all the parts printed again, including the frog, now with mounting holes and wing rails.

Speaking of the frog, that “SketchUp is unforgiving when backtracking to a mistake made many operations ago” was spot on. I had already reworked the hold downs on one side, effectively half the frog modified, when it became apparent there was a major mistake made many operations ago. Sometimes this free program is worth exactly what I paid for it… Nothing.

Feeling Froggy

So as not to lose anything I had done so far, I copied the frog to another drawing and began the tedious “Undo” process back to the single misstep that caused the problem. This is where the history of operations is so valuable in other applications like FreeCAD. Made an error? Just go back and fix it and the change propagates forward without further impact.

Not SketchUp. Rewind then redo EVERYTHING since the mistake. Thankfully I caught it with only half the frog reworked. After that adventure, I was very careful to check my work frequently, especially when adding the guard rails to the frog tie strip section. But that’s the last design to finish for now and it’s printing, with an estimated 6 hours and 39 minutes to go.

While that’s printing I’m test fitting the previous section, the closure rail tie strip, and run into a fitment issue with the last three ties before the frog section. Even though I centered the hold downs around the 14′ diameter stock rail in the design, they’re a very tight fit, like they’re offset too much toward the middle of the tie. I mark them with a red dot in the design to keep track of these fitment issues.

Test Fitting

I’m wondering if it’s just that one piece of rail that has an excessive bend at the end, but then how did it fit through all the rest of the ties with no problem? Why these last three ties? We’ll just keep that in our back pocket for now. This is just the prototype, and only the second iteration for that matter.  I did find two other oversights that I’ve already corrected though.

One is a missing strip section between ties and the other a missed section of a tie on the end to finish making it solid. Not bad for a prototype, and that’s what this stage of development is for, to catch any hiccups before devoting to production… with a whopping production volume of one. Maybe two if I make a mirror image and use it on the other leg of the wye.

After allowing the frog tie section to cool when it finishes printing, the test fitting continues. The rails slide right in with ease, through all the tie strip sections, with the one exception of the closure section already mentioned. The rails fit snugly, yet loose enough to easily assemble. The redesign paid off. Totally worth the days of effort!

Next Steps

I’m impressed with the new printer. Only had one issue with it so far, and a self-inflicted one at that, a clogged nozzle. It’s my fault for using that old brown filament that’s been sitting out collecting moisture and dust, a surefire way to clog a nozzle. The filament became very brittle toward the end of the spool and ended up leaving broken pieces throughout the system when rewinding it.

At least now I know where to look for filament issues, how to take everything apart, and how to resolve them in the future. I ordered a couple replacement nozzles just in case a future clog can’t be cleared. It was a frustrating couple of hours though while I struggled to figure it out. Hours better devoted to redesigning and printing the latest iterations.

Next is testing multi-color printing. The multi-color slicing by height feature works well. And it’s all automatic! No pausing mid print to manually swap filament then resume. I may want to adjust the “flushing volumes”, if that’s even possible. That’s the amount of plastic “pooped” out to be sure the previous color is flushed and replaced with the next color before printing with it.

Thankfully AnyCubic was kind enough to include the print files for a “poop bucket” in the printer’s memory so I didn’t have to design it myself. It’s HUGE! It takes up nearly the entire print height and used more than half a 1kg spool of filament! But now I don’t have to worry about the piles of plastic poop accumulating on, around, and under the old printer anymore. It can make quite a mess.

Behold! The Magnificent AnyCubic "Poop Bucket"
Behold! The Magnificent AnyCubic “Poop Bucket”

Decisions, Decisions

Only ten days in, that’s where we’re at with our curved switch. All that’s left is “finessing” the rails to the proper lengths and shapes. I’ll need to bend a set of rails to the proper radii to start with. The stock rails are fairly simple, but the remaining rails need cut to size for the point, closure, and frog sections. Then grinding the point and stock rails to size. Lots of fun… Not!

I’m already thinking about how to go about that rail shaping. I don’t have a wheel or belt grinder. A Dremel with the proper grinding stones is about the only thing I have on hand. There’s still so much work to do in the garage to make space for anything on any bench that my options are limited for now.

Buying a new belt grinder makes sense for production quantities, but until I have the bench space for it, where to put it is the bigger issue. Almost the same issue for the Dremel drill press, except it’s more about getting to it. It’s sitting on the bench behind all the stuff that has to move somewhere else just to gain access to it. Either way there’s some bench cleanup in my very near future.

With any grinding option I’m thinking that a jig, or jigs, to hold and guide the rails would help ease the task of shaping them. The point rails need a good bit of material removed from the side that meets the stock rails. And the stock rails will need the foot removed on the point side to allow the point rail to snug up to it when that route is selected.

Grooming The Rails

Speaking of point rails, I need to modify the design to remove the ends of the ties around the throw bar and add mounting holes for the switch machine. Essentially make them hollow on the ends again, enough for the mounting brackets from the switch machine to fit and secure them with screws. Another option would be to just print the mounting bracket as part of the ties themselves.

I like the latter option better, more like prototypical headblocks, with the switch machine mounting hardware to secure it at the headblock ties’ ends, and no supports to remove. But I’m getting ahead of myself again. We’ll come back to this later. Until I have room for that new belt grinder, I can still bend the rails to the correct curvature and use the Dremel saw to cut them to length.

Up until now I’ve been using the rails from Aristo-craft 14′ and 20′ diameter curve sections with the their tie strips removed to test the fit. Time to switch to the actual rails we’ll be using. There’s still plenty of flex track rail left from our last day trip over to Pinellas Park, maybe 50′ of track, or 100′ of rail. Each rail is 10′ long, so two should be enough for the switch with some to spare.

Rough math says two 4′ long sections of track, one for each route. That’s roughly two 8′ long pieces, with maybe ~2′ leftover from each 10′ rail? The stock rails are easy to figure, and the Aristo-craft 20′ diameter curve outside rail provides an accurate template. The 14′ stock rail is more a “guestimate”, but the 20′ diameter curve inside rail is a close approximation, if not slightly too long.

Bending The Rails

Before any rail is cut, it needs bent to the correct curvature. Using enough of the Piko flex track tie strips to hold the two rails together and the rail bender, they’re coerced into the 20′ diameter curvature to start with. Again, the Aristo-craft 20′ diameter curve section provides an accurate template to compare to while bending and measure against when cutting the rail to size.

Next are the 14′ diameter rails, then the closure and point rails, and lastly the frog rails. A quick deburring with the diamond file to avoid slicing fingers open on the sharp edges and the stock rails slide in nice and easy. The 14′ diameter stock rail doesn’t seem so snug where it did previously, but somehow I managed to cut the 20′ diameter closure rail too short!

Thankfully I made the frog removable, which allows the closure rails slide right in> Then the frog is fastened in place using three M2.5 screws. From there the frog rails and the diverging route tie strips. The point rails have a single hold down which acts as the hinge, or pivot point, of those rails. Without some means to hold them in place they keep falling out. Time to work on that throw bar.

Honorable Mentions

There are a few things worth noting before diving into the next design modifications. First is the recent innovation of High Temperature PLA (HT-PLA) by PolyMaker and how it solves a key design limitation when 3D printing the curved switch parts, heat resistance. Standard PLA is no match for the Florida heat! Second is the foray into OpenSCAD.

PLA lasts only days before warping, as we found out the hard way with the Grand Hotel “skin”. We need a quick way to test this HT-PLA in the baking hot Florida sun. The quickest way there is to print something we’ve already designed, like one of those brick walls from the Downtown Marketplace storefronts. But instead of manually editing it to make it thicker, it’s time to try out OpenSCAD.

With the switch on the back burner until a decision on a grinder is made, time to look at new opportunities using the HT-PLA material. In all the discussion about FreeCAD vs. SketchUp, OpenSCAD was never mentioned. OpenSCAD is a way to programmatically design 3D models. All those tedious manual foot clamp changes could have been an easy change to a parameter in OpenSCAD.

To see more about how we tested HT-PLA and how we solved other problems for a number of mothballed projects waiting on a different solution, take a look at our cut stone retaining wall post.

A New Grinder

Getting back to that throw bar, we need the point rails and stock rails shaped to accurate place where the throw bar mounts to the point rails to provide the proper wheel flange clearance through the non selected route. How to mount the point rails is a different story. My thought is just use the Dremel drill press to drill holes in the foot of the point rails, tap, then secure with screws.

Nick has a lot of experience working with stainless steel and reminds me it requires slow speeds and heavy pressure. If anything the Dremel is high speed and low pressure. That works great for burrs and grinding stones, but not so much for drilling stainless. So much for that idea. At least I don’t have to worry about how to extricate it. The time has come for a new belt grinder.

Quick trip to Harbor Freight finds a 4″x36″ belt grinder that will fit the bill nicely. Once home, it sat in the box for a day or two before I cleared a spot for it on the corner of the bench next to the table saw parking area. Definitely made quick work of shaping those rails, starting with the point rails. The only difficulty is getting close enough to make the sharp transition the stock rail’s foot.

Finessing The Fiddly Bits

With that much said and done, the hard part is getting everything just right. The fit between the rails for the switch portion of the turnout takes some fiddling and finesse to get them finely tuned. Otherwise, the result is derailments as wheels “pick the points” and equipment ends up following both routes instead of the selected one.

Before we can even get to that point, we need a throw bar to secure the point rails together, yet space them apart by just the right amount. Again, just enough to clear the wheel flange through the non selected route. It takes quite a few iterations just to get those dimensions correct. Next thing that needs figured out is how to secure the point rails to the throw bar.

The Aristo-craft switches have a hole drilled and tapped into the web of the point rails to accept a 2mm machine screw. The screws pass through the throw bar and secure it to the the point rails. Originally I thought about doing something similar, purchasing the tap and correct drill size to do so.

But as Nick had said, using that high speed Dremel tool is a sure way to work harden the stainless steel and snap the drill bit right off. Last thing I want to do is bend more rail, cut it to size, and grind to fit a point rail all over again. Out of curiosity, I try using the 1⁄16″ hex shank drill bit by hand. Can’t go much slower than that! Pressing hard and working slowly does the trick.

Adding A Switch Machine

In no time at all both point rails are drilled. But rather than go into the web, I just drilled through the foot. There’s not enough “meat” there to rely on tapping the hole, so I used self tapping screws. Although they’re not really meant for metal, they work well enough to capture the point rails and secure them to the throw bar. Getting the placement and relief right takes a few more iterations.

Moving on to the switch machine and how to mount it. Because the switch machine itself secures the headblock ties at the proper distance apart, originally I was thinking about just modifying the design to remove the mount points from the two tie strips and incorporate both together as a single, separate unit. It would actually be two designs, one for inside throw and one for outside throw.

That way the only mounting hardware is on the switch machine itself. I opted for a compromise design that requires just a single adapter and can be “press fit” from beneath into recesses in the headblock ties. That way it can rotated to the proper orientation no matter what side the switch machine mounts to and the benefit of mounting hardware on just the switch machine itself remains.

As always, that design takes a number of iterations to get everything just right too. Using a standard Aristo-craft manual switch machine, that familiar over center “snap” action is now selecting which route through our curved turnout! Started testing clearances by running a single wheel set through each route then graduated to using an old style passenger car. It passes with flying colors!

It’s A Big Un!

If you think the 3′ long #6 and wye switches are impressive, you should see my 4′ long (~122cm) curved switch! My first rough estimate puts the frog somewhere between a #5 and #6. But it’s a curved frog, not straight, making it difficult to tell exactly what the “rise over run” values are. It does resemble the #6 frog fairly closely, so probably closer to a #6.

It’s a bit unwieldy and getting it from the workbench and out the back door to the wye was a real feat, but it fits like a glove! Perfect! Can’t wait to see whether it works or just derails everything. That depends a lot of on how well it stands up to the pups pounding on it when chasing the ball or the occasional squirrel that has the audacity to try to run along the top of the new fence.

It’s designed to be a “drop in” replacement of an Aristo-craft 20′ diameter curved section and that’s exactly how it fits. Just need to perfect those double insulated rail joiners and we’ll be all set to test the operation. At least manually. It’s going to take a bit more effort to actually get the trains running again and subject it to the true test.

Next Steps

You may ask why I don’t just buy some insulated SplitJaw clamps. At $13 plus shipping for two stainless steel insulated clamps, that gets real expensive real quick. Granted, I can get ten for $30, but compared to $300 for 60 standard clamps, $3 vs. $5 per clamp, it seems like a good deal all of a sudden. I have access to milling equipment, so I may end up making my own.

They don’t make insulated double length rail clamps, so I’ll just print the insulated part and use parts from the standard clamps to make my own. While I’m tinkering with those, I take another foray into OpenSCAD, this time to create replacement tie strips. OpenSCAD is covered in more detail in our cut stone retaining wall post. Check it out if you’re interested. Now back to the story…

A box of twenty-five Piko11″ tie strips is around $125. That’s ~$5 each! I calculated 3D printing our own at ~$2 each, but let me check my math on that one. If we can print twenty-five of them from a single 1kg spool of filament costing $25, that’s $1 each. Two spools => $2 each. etc. The slicer says 88.53g of filament, or a little over 11 per spool, so $2.22 each. On sale at $20, that’s $1.76 each.

Beyond all that, there’s more work to do to get to a final product. Once we have trains running again, we’ll see if the prototype switch can withstand the true test. Will it hold up or fall apart? What else needs done to make this a reliable part of our Barkyard RR? We’ll find out soon enough. Spoiler alert, we cover running trains in our final installment of replacing stringers.

 

Disclaimer – Not Sponsored

I should mention that the Barkyard is not sponsored by AnyCubic, PolyMaker, Elegoo, Sunlu, or any of the host of other manufacturers of 3D printers and filament or any other entities, like Harbor Freight. I don’t think they’d care much for my nicknames for them anyway, like Horrible Freight, Hazard Fraught, etc. No freebies or evaluation promotions here. This is all paid for out of pocket.

Question? Concerns? Leave A Comment!

If you’re interested in obtaining the STL files to print your own curved switch, leave us a comment and we’ll be happy to provide them to you. Also, if you have any other questions or concerns, please feel free to comment on this post. In any case, you’ll need to create a user account to do so. We don’t use any personal information for marketing or to spam you (see our privacy policy). You’ll receive a verification email. Reply to the link provided to verify your email address. It’s all automatic. No waiting on moderator approval! No spamming your inbox with useless advertisements and “Special Offers”. None of that nonsense. We do it this way to prevent bots and spammers from detracting from your experience.

More to come. Stay tuned!

 

Making A Curved Turnout

Welcome back to planet Unobtanium! If you thought finding Aristo-craft #6 or wye switches was difficult, or anything in stainless steel for that matter, good luck finding anything curved. As rare as they are on the prototype, it’s no wonder they’re nonexistent in garden scale. If you know of anyone who makes them, or made them, please leave a comment and let me know!

For the longest time I’ve struggled with how to “complete” the downtown wye. Due to space constraints, a standard switch won’t fit. We’ve designed ourselves into a corner, so to speak. In this case, a 14′ diameter semi-circle of track, and a need to escape it at the quarter circle mark to join with the diverging leg of the wye.

We “cheated” before by replacing one of the 14′ diameter sections of track with a 20′ diameter section, connected directly to the diverging route away from downtown. This left no way to enter the downtown leg of the wye from that direction. That leg was still accessible from the direction of the actual wye switch, but now nothing more than a dead end spur.

Necessity’s A Mother

The wye switch was removed as well. The leg into downtown from the south has a wide radius switch, but that was also rearranged to better fit continuous operation. That entire section to the south leads to the lower loop around the deck. To avoid the need for a reverse loop controller, automatic or otherwise, the switches are placed “toe-to-toe” rather than “heel-to-heel”.

This one’s definitely going to need a picture (or three). I’m waving my hands over here trying to describe it and can already see the blank stares… We’ll get to that shortly. For now, let’s just say we side stepped this issue in favor of continuous running. Eventually we’ll need that auto-reverser, but that’s another project all by itself.

We’ve finally reached the point of needing that curved turnout. Which means it’s time to design one and start making it ourselves. To that end, I resurrected the homemade #5, an old tangent to 14′ diameter switch design I started drafting up ages ago. I shelved it when I realized I was in over my head, still a novice with the SketchUp software and 3D printing.

A New Hope

I last touched that design in early March of 2020 and it shows! I’ve gained a lot of experience in those six years though. Now I’m putting it to the test on the homemade curved switch. All my time has been devoted to this new design, when I’m not working on replacing the rotted stringers that is, which means anytime during the week when I’m not working my day job.

All that dedication paid off. In a little less than a week the preliminary design is complete and the prototype tie strips have all been 3D printed! Test fitting the tie strips for the heel and point rail ties suggests the fit is “a bit snug”. And by a bit snug, I mean I had to use the tack hammer to “tap” the inside 14′ diameter stock rail into position.

The remaining tie strips are printed and all the support material removed, all but those on the frog ties. Some background on the design of these tie strips. Each tie is connected to the next by a strip of material in order to keep them spaced apart and in the proper position relative to their placement along the switch. Hence the name “tie strips”. But I’m getting ahead of myself again.

Technical Difficulties

Ann tells me this is probably too technical for folks that haven’t looked at turnout (switch) design before. Too many unfamiliar terms and a bunch of hand waving around them without any kind of visual reference to help understand what I’m talking about. Let’s address that. The term “switch” refers to just a portion of the actual “turnout”, but the names are commonly used interchangeably.

Hopefully the diagram will be helpful. When discussing the stock rails, it means the two outside rails. The point rails are actually the switch part of the turnout, meaning they switch the route through the turnout, normal (usually the straight path), and reversed or diverging (usually the curved path). The closure rails are a continuation of the point rails, past the hinge point, as they’re closing in on the crossing (frog) of the diverging rails.

The frog has wing rails and guard rails help to guide the wheels through the frog. The idea is the wheel tread slowly leaves the wing rail as it also slowly begins to ride on the frog, smoothly transitioning from one to the other, starting around the point of the frog. That’s probably enough about switch design and far more than most folks would care to know about it. Again, hope this helps clear up any confusion.

Design Considerations

The tie strips are designed to be around 12″ at the longest, mainly due to 3D printer build volume constraints. The new 3D printer, an AnyCubic Kobra S1 Max, arrived not even two weeks ago and has a build volume of 350mm x 350mm x 350mm (13.77″ x 13.77″ x 13.77″). Needless to say I’ve been anxious to put it through its paces and see what it can do.

I’ve already encountered the “out of filament” event. An event that revealed what a total piece of crap the “old new” Sunlu 3D printer is when it comes to filament management. It certainly detects when it’s out of filament. It complains about it and asks for the filament to be replaced, but then loses its mind after that, requiring a power off reset to recover from it!

The AnyCubic? It functions the way the Sunlu should have. When it detects it’s out of filament, it homes the print head, remembering where it left off. Then it prompts to confirm refilling the slot in ACE cabinet. Once it detects the new filament is inserted it primes the system and awaits the request to resume printing, which it does, right where it left off! It’s a dream come true.

A Poor Assumption

It’s not all rainbows and unicorns though. As I mentioned, the fit is a bit snug. The ties are fragile, cracking and splitting along the layer lines when pressing them onto the rails. But by far the biggest drawback of the initial design is all the support material. It takes about half an hour to remove all the support material from each tie strip, using needle nose pliers no less!

Let me step back and describe the original design approach before we go much further. The design is “copied” from the original Aristo-craft switch ties. The thought is it worked for them for years, so it should provides clues where to start, and should be a good jumping off point for our design. Well, that was a poor assumption, at least for the ties themselves.

There are other limitations to the Aristo-craft switch design, but we’ll get to those shortly. Their tie design was meant to address injection molding and manufacturing constraints that we don’t have. We do have constraints, just not the same as those. Our constraints are related to 3D printing and the materials available that can survive the heat.

Differing Design Constraints

The Aristo-craft design uses “hollow” ties with thin walls and openings on the tops of the ties where the rail “foot clamps” live, presumably to conserve the amount of material injected per part into the molds and facilitate the release of the parts from the molds. Parts in this case refers to the tie strips, not just single ties.

The Aristo-craft injection molds themselves provide the “overhang” support for the underside of the top of the tie. We don’t have that luxury when 3D printing. Any overhang of more than a 50° angle from vertical will cause issues. With nothing to support the molten plastic, it droops and deforms. Those familiar with 3D printing will know it as “bridging”.

Successive layers above the area of bridging depend on those previous layers for support, now missing and drooping because of lack of support beneath them. Again, those familiar with 3D printing know that supports are “waste” material. They get printed along with the desired part, but are only there to bridge the overhangs and support the layers above.

Refining The Design

After printing is complete, the supports must be removed, usually tossed in the trash. Wasteful, but necessary when the desire is to print as one piece, not many that need joined together in some fashion. For tie strips, we could certainly print a dozen or more separate ties, then print two strips of rail foot holds, one for each rail, and glue them all together.

I’ve not tried that approach, but have to think it would take just as long to glue a tie strip together as it does to remove all that wasted support material inside the hollow ties. A better approach would be to just redesign the ties to be “solid”, that is to say a defined number of walls in thickness with a certain percentage of infill inside them.

The ties don’t need to be hollow to begin with. That was an injection molding constraint. For not much more material than would have gone into printing the supports then thrown away, what used to be waste material is now incorporated into the tie itself, producing a much stronger tie in the process. If it’s going to get used anyway, may as well add it to the part!

Further Refinements

I kicked off printing the frog tie strip before getting out in the Barkyard, working on more stringer replacements. It’s more than a five hour print, which gives me plenty of time to refine the design for solid ties and put together a couple more PVC stringers. The tie strips for the diverging routes all use a single tie model, so updating the design fixes those eleven ties all at once. The rest of them? Not so much…

The print of the frog tie strip had long since finished by the time I knocked off for the day from replacing stringers in the Barkyard. I hadn’t planned on being out there all day, but managed to correctly re-construct the two wye legs that had been plagued by my previous misguided assumption about the wye switch. With the needed curved switch about to become a reality, it made sense to correct the mistakes of the past.

I removed frog tie strip from the build plate flex sheet and kicked off printing those diverging route tie strips. When they were done printing, I started the process of removing all the supports. This time it’s limited to just the connecting strips, which easily break off by hand, and the rail foot clamps. Those still require the needle nose pliers, popping them out from the top into the hollow area beneath. Quick and easy!

I tried removing the supports from the frog tie strip, this time concentrating on removal of just the supports for the foot clamps. The rest of the support material in the hollow of the tie can just stay there. It’s not visible, so why bother? I stopped short of removing them all though.

Further Refinement Considerations

Those diverging route tie strips are much stronger with infill and the ease of removing the supports is another vote in favor of this redesign. Another consideration for refinement is the tight fit of the foot clamps on the rails. I had already eased the fit by ten to twenty thousandths of an inch (¼mm – ½mm) in places where the rail angle compared to tie is large.

I forgot to add the supports for the foot clamps for the redesigned print and accidentally discovered they’re unnecessary! It’s a Bob Ross “Happy Accident” moment. So now we’re down to just the strap supports, which are easily removed in a minute or two. That’s a helluvan improvement over the half an hour for the previous designs.

Let’s rewind to the original design idea for this curved switch to better understand that last statement about rail angles and foot clamp clearances. Even with standard tangent to diverging curve switch designs, on the diverging route the rails fall at an angle to the ties. Eventually toward the end of the diverging routes, the ties resume their normal perpendicular orientation to the rails when they no longer interfere with each other.

Now consider this is a curved switch and regardless of which route is taken, we’ll call them them normal and diverging, since tangent doesn’t really seem to fit, both the normal and diverging rails will always be at an angle to the ties, save for those final diverging route ties. Given both routes are curved, one way to minimize that angle is to arrange the ties to the average curvature.

Initial Design Constraints

In our case, midway between the 14′ and 20′ diameters is 17′. Starting with the original tie design from way back, they are arranged every half degree for the full 22.5° curvature of an entire 20′ section. I made this a constraint to avoid the tragic outcome from my previous mistaken assumption that the Aristo-craft wye switch was a full 20′ diameter section. Ours is an entire 20′ diameter section long, coming in at around 4′.

When a full 22.5° 14′ diameter section is placed over the 20′ section, it’s only long enough to meet where the frog will sit! Anything less than a full 22.5° section of 20′ diameter track would be less than a complete switch. I arbitrarily added an additional 7.5° to the 14′ diameter route to ensure the ties from sectional track segments won’t interfere with each other.

What can I say? A hold over from my HO days where the #4 switches need a 1⁄3 18″ radius section for the switch to replace a single 18″ radius 30° curve section. Those legs of the wye already use flexible track segments bent to fit properly. Worst case is an extra 7.5° needs removed to fit with the new curved switch in place.

Additional Design Refinement

Getting back to the design decision to use a 17′ diameter tie layout, each tie needs to be adjusted because of this decision, more so than if it were a tangent / diverging route switch. Both routes need to be adjusted, not just the diverging route. By adjusted, I mean the length of the tie and the position of the foot clamps based on rail position as well as interference fitment.

That’s where the 10 to 20 thousandths figure comes from. Each of those 48 ties needs careful consideration, from centering the foot clamps over the rail foot, to sighting down the length of the rail from the inside to verify clearances from the tip of the foot clamp to the web of the rail. It’s like using X-ray vision to eliminate any interference between them.

One other outcome of running out of filament is the brittle nature of the replacement filament. Don’t even look at those foot clamps wrong or they snap right off!. Finding out why this filament was so inexpensive. Definitely not a bargain. Never buying that stuff again. I’m guessing what I’d been printing with before was PLA+ and this latest stuff is just plain PLA. Dunno. It’s just plain crap for sure.

Real World Considerations

The brittle nature of the filament coupled with a lack of complete support removal is a sure way to snap it right off when attempting to test fit rail. So one more refinement will be to back off the foot clamps another 10 thousandths as well as raise them all by 10 thousandths. It’s also a vote to just reprint those other ties strips using the design refinements.

But that’s not as easy as changing one model to fix all of them like it was with the diverging route ties. Every one of those remaining switch ties is unique. Most have two additional rail foot clamps beyond the original two the model they’re based on came with. The exceptions are the approach ties to the point rails and the ties under the point rails. just sixteen of them out of the 48 switch ties.

I’m going to cut this one short for now. If I somehow manage to make substantial progress tonight, then I’ll come back and update this post. Otherwise, stayed tuned for Part II. There’s plenty more to be done to make this an operational switch, but so far there aren’t any show stoppers that would interfere with that goal.

Question? Concerns? Leave A Comment!

If you’re interested in obtaining the STL files to print your own curved switch, leave us a comment and we’ll be happy to provide them to you. Also, if you have any other questions or concerns, please feel free to comment on this post. In any case, you’ll need to create a user account to do so. We don’t use any personal information for marketing or to spam you (see our privacy policy). You’ll receive a verification email. Reply to the link provided to verify your email address. It’s all automatic. No waiting on moderator approval! No spamming your inbox with useless advertisements and “Special Offers”. None of that nonsense.

More to come. Stay tuned for Part II!

 

New Stringers – Part II

Welcome back! We’re still welcoming Spring with new PVC stringers. If you missed our first post, you may want to start there first. This is a continuation of what we started there. Except now it’s well beyond the first day of Spring, nearly the end of April at this point, and we’re still working on replacing stringers! This post covers another three weekends of effort.

This is taking much longer than expected, but continued improvement each weekend brings us closer to our goal of running trains. We left off with all the elevated sections painted and installed. In addition, the downtown mainline, station siding, and long siding are installed. Those took longer because those stretches are on the ground and more rotted stringers needed dug out first.

The track is installed as well, with the one exception of the stretch where the bridges will go. For now it’s just a straight elevated section waiting for track and bridges. Originally the thought was the approaches would be of trestle construction, but now I’m leaning toward laced steel girder supports and plate girder bridges. That can wait until later. We can run trains without any of it.

 

Fixing The Wye

Hadn’t really planned on doing anything more than what’s necessary to replace the 20′ diameter track section and wye switch with 14′ diameter sections. Essentially we want to “hardwire” the Downtown loop to return to the mainline, reducing the layout to its original “dogbone” roots with two loops, one Downtown, and one over the deck.

The thinking was maybe we’d restore the wye in the future. Well, the future is now. What prompted this change? It all started with having to replace the stringers on the 20′ diameter section of the Downtown loop. It ended with finding the old homemade #5 switch design and bringing it out of mothballs. Somewhere in between we discovered that fixing the wye would be easier than not.

Since the track was still in place over the 20′ diameter section, the assumption was the stringer beneath was still in good shape. That was a poor assumption. Oh well, we’ll just make another 20′ diameter replacement while we’re at it. Slowly but surely that stretched into the next 14′ diameter section, then the next, and another after that.

Working toward the wye switch it became apparent all the wye stringers were rotted and need removed. Replacing each new section of the 14′ diameter stringers, it soon became apparent the posts weren’t arranged in a 14′ circle either. Turns out we’ll need another 14′ diameter stringer to reach the wye switch as well, once the remaining rotted stringers are removed that is.

 

If It Doesn’t Fit, Force It…

Force fitting those 14′ diameter legs of the wye may have made sense at the time, but now leaving them that way is more trouble than making it right. Time to break out that wye switch and take some measurements. We’re trying to locate the centers of those 14′ diameter circles, one on each side, based on the true geometry of the wye switch. But we’ll need something straight at least 7′ long.

Hmmm…. What do we have that is both long enough and straight enough? We have a whole stack of 8′ long PVC 1x2s not yet assembled into new stringers. One of those would certainly fit the bill. Marking out the centerline on the turf with a sharpie is close enough, but reminds me of previous opportunities lost without a more permanent center marker.

There has to be a better way to do this. Time to find one of those spare “turf nails”. Found a bunch of them in one of the drawers in the toolbox, and two different sizes no less! The idea is to “pin” the center with one of the larger turf nails. Beyond that, by attaching one of those 1⅝” spacers to one end of the 1×2 and drilling a hole to fit the nail marking the center at the other end, we have an accurate compass.

With our new PVC “compass”, we can “sweep” a 14′ diameter circle, holding the stringers in place with that spacer. It fits nicely between the two sides of the stringer and holds it in place while confidently driving a post into the correct location. That involves pulling out the existing incorrectly located posts with a set of Kleins then accurately smashing them back in with the sledge hammer.

All Kinds Of Wrong

As helpful as our new PVC compass is for laying out the curved stringers, it also excels at pointing out all the mistakes in our original geometry. Both legs of the wye were off by more than twice the width of the track! No wonder the track refused to cooperate and go where it was supposed to without a fight. All kinds of wrong.

On the North leg of the wye, the closer it gets to where we need that curved switch, the more the radius relaxes into a wider curve. On the South leg, the closer it gets to those toe-to-toe switches, the tighter the radius gets! If you look closely at the pictures, you’ll see how far off the black edging is now. Good thing we’re using flex track for both curved legs!

It may take some time with the rail bender to finesse the wonky curved flex tracks to fit properly, but it’s totally worth the effort. Both stringers now follow a smooth curve that fits the desired geometry. I just wish I’d painted those stringers before fastening them together! Nothing some strategically placed masking paper won’t handle.

So kind of a funny aside. A while back I asked Nick to pick up a couple cans of brown spray paint for me from Lowe’s. He got me two of the fancy adjustable nozzle Krylon brown and two of the 2X espresso color. I used those up weeks ago. The next time I was there, Lowe’s was out of the 2X espresso I wanted, so I got three with the fancy nozzle in dark brown. They’re also gone now.

Last time there I bought all the 2X espresso they had, the three left on the shelf and the remaining case of six I had to have an associate fetch from the rack high above using the huge rolling ladder thingy. After painting those wye stringers, I’m down to my last four cans! But I’m getting ahead of myself.

The only reason we’re talking about painting in the first place is because of protecting the PVC from Ultra-violet (UV) radiation, which breaks the bonds in the flexible long chain polymers, making it more and more brittle over time. Paint is a means of protecting the PVC from the UV degradation of baking in the hot Florida sun. An added bonus is it looks much better than bright white!

Time To Take A Fence Break

We almost got the wye finished, but had to stop and make sure we’re ready for the new fence to go in this coming week, the first full week of May (2026). So we also spent this last weekend pulling out the rest of the track and rotted stringers from behind the shed in preparation for the fence builders to come in and replace the fence. Wasn’t much left but the track itself and just a single 10′ diameter wood stringer still in fairly good shape.

Even that totally destroyed 3′ section of track came out, the one that hurricane Milton blew down a big chunk of the tree on that caused all the damage. Speaking of that destroyed 3′ section, I managed to get both rails straightened out and the tie strips back in place and screwed securely to the rails. Like it never happened! I was amazed that just sighting down the rails and some time with the rail bender was all it took.

But that wasn’t the only piece of track repaired. Add two 5′ sections to the list from yesterday. Just about every piece of track needs disassembled and the tie strips “reseated” over the foot of the rails before the track can be put back in place. Anyone who’s ever dealt with those annoying little Aristo-craft screws knows what a pain they are. My big hammy hands make it even more difficult, inevitably losing some of those fumbly screws in the process.

As an example, one of those 5′ sections was missing every fourth screw. I have some replacements but they only thread in a little over a turn before binding, like they’re the wrong thread pitch, so I gave up on that. Some are better than none. When you get right down to it, are they really necessary at all? Those Piko tie strips for the flex track have none and still hold the rails just fine.

Fence Break’s Over!

Fixing the track is about all we’re able to do while they remove what’s left of the old fence and basically build our new board-on-board fence in place, from scratch. I say they, but it’s basically one very dedicated individual, John, and he knows his stuff! Over the course of four days he nearly single handedly built our new fence. He had a “new hire” one day, but he quit and left early on his first day! We’re simply amazed by the quality and craftsmanship. And it looks awesome!

Judge for yourself. All but one of the pictures so far show the old, dilapidated fence in the background. Those pictures that follow will have the new fence in the background. Ann’s already out there stringing up the lights, and doing it the way she wants them done this time around, stretched straight and level. No sagging allowed! We even rerouted the dedicated extension cord around the back of the garage instead of draped over the track in front of the shed. Much better!

Time to get back to replacing the stringers. All the curved stringers we need are already finished, painted, and installed. Time for a bunch more straight ones. Two for the bridge section by the deck, two for the straight leg of the wye, and another to complete the station siding. Another weekend, another set of stringers installed. All but the straight leg of the wye. That’s going to take a LOT more work to finish.

Not only does the dirt need dug out, but there was turf under the old stringers, meaning it will need cut out of the way first, just to be able to get to the dirt under it! We’ll save that for next time. For now the progress is impressive. And more than we originally planned. But to make the wye a reality, we’ll need that curved switch. Good news everyone! That’s already in the works. I spent the week the fence was installed working on the design, captured in this post.

For A Limited Time Only

I’d been gathering the footage of the progress from the surveillance cameras, thinking they could be spliced together into a sort of time lapse montage. But then I missed the window to grab the footage from a couple weekends now. I’m surprised by this since I’ve been able to go back more than a week in the past. I can’t remember the last time I wasn’t able to. Oh well, I’m down to my last 3GB on a 4TB drive, not sure where I would have put it anyway!

Add the footage of the fence installation to that and we broke the bank, so to speak. I hastily rearranged data on the network storage server and removed duplicated items to make space for this video and more. I’m not real comfortable with the single point of failure state that left a lot of the existing captured video in, but I haven’t done anything with it years later, so chances are I’ll never do anything with it anyway and it’s just wasted storage. Time will tell.

For now, we’re busy with a single goal. Get. Trains. Running. Will we get there by Memorial Day? We’re definitely cutting it close with just one more weekend until Memorial Day weekend. I hate to leave you with a cliff hanger, but if you want to find out, you’ll have to stay tuned for Part III. I will admit we’ll be pushing it just to get all the stringers replaced, let alone all the track relayed.

 

Question? Concerns? Leave A Comment!

If you have any questions or concerns, please feel free to comment on this post. In any case, you’ll need to create a user account to do so. We don’t use any personal information for marketing or to spam you (see our privacy policy). We do it this way to avoid scammers spamming our posts. You’ll receive a verification email. Reply to the link provided to verify your email address. After that, it’s all automatic. No waiting on moderator approval! No spamming your inbox with useless advertisements and “Special Offers”. None of that nonsense. We do it this way to prevent bots and spammers from detracting from your experience.

More to come. Stay tuned for Part III!

Welcoming Spring With New Stringers!

Welcome back! We’re welcoming Spring with new springers, er… stringers. To celebrate the first day of Spring, we got out in the Barkyard to begin the annual stringer replacements. Well, technically it’s the second day of Spring, but close enough. We never expected this to become an annual event, but that’s what it is now.

Learning the hard way that modern wood products just don’t stand the test of time out in the elements. Not even when heavily treated to do so. Those wood stringers offer a sturdy base for our track and elevate much of our rail above ground. Inevitably those wooden stringers rot. Last fall, we decided to try using PVC to replace a few rotted sections.

There are advantages to using PVC trim over pressure treated (PT) lumber. First is reduction of effort and waste. To construct wooden stringers, we rip a 2x4x8′ stud into not quite a dozen ¼”x1½”x8′ slats. It’s labor intensive considering the time spent at the table saw and it’s wasteful as each rip turns ⅛”x1½”x8′ into sawdust. That’s one third of the raw material converted directly to waste!

Another advantage of PVC stringers is ease of assembly. Each side of the stringer is now a single ⅝”x1½”x8′ PVC trim piece, not three slats that all need trimmed to different lengths when using the curve templates. I built those templates to help ease assembly, wrangling all six slats and a dozen spacer blocks into some semblance of order.

Let’s Do This The Easy Way

Now it’s just a single pass with a pair of the PVC 1x2s, drill and screw each to the spacer blocks, then trim either end and done. It still takes about an hour to assemble an 8′ section of stringer, but it saves about another hour of ripping a 2×4 into slats, not to mention the countless hours of removing rotted sections and replacing them every year.

Speaking of those jigs, they’re not really necessary when using PVC. Assuming the posts are arranged in the desired pattern, circular or otherwise, just attach the spacer blocks to one side then fasten that in place along those posts. Attaching the remaining side is easy enough using clamps to hold it in place while fastening it to the first side and posts.

So far we’ve used the 14′ and 20′ curve jig. The 10′ diameter curves could be a different story. We skidded the shed out from the fence another 8″ a while back with the hope of fitting larger curves to replace those tight 10′ diameter sections. They were enough to get us up and running originally, but now we have flex track and a rail bender to fit any size curve.

Getting A Head Start

Every year there’s a push to get trains running again. This year we’re starting earlier than most, in the past usually waiting until May to get trains running by Memorial Day. Some years that even stretched to July 4th. And every year it’s the same thing. Replace the rotted wooden stringers. As we said, it’s become an annual event.

Those concrete roadbed “bricks” we’re experimenting with work, but are much more labor intensive than posts and stringers, and nowhere near as sturdy and immoveable as we thought they’d be. Still working on how to streamline that process… Comparing the ease of replacing the rotted wooden stringers with PVC ones with the amount of effort using concrete bricks, it’s a no brainer!

So far we’ve replaced about 100′ of stringers, both straight and curved sections, but we’ve also taken up more than 300′ of track where the stringers had already rotted out over the past year or so and no longer held the track. We’re still behind the curve for getting trains running by Memorial Day, but we’re working hard to make that happen.

Just Enough

The plan is to replace just enough track to have a continuous loop trains can run on. This would consist of the downtown loop, that North leg of the wye loops around through downtown along the mainline back to the elevated sections. The elevated sections need bridges in place to run trains past the deck and back to downtown.

The lower loop around the deck and the other legs of the wye will have to wait. Essentially the mainline Downtown connects to the wye switch (West). The diverging legs of the wye arrangement go left (South) to the deck and right (North) to the downtown loop. The only thing missing to make it an operational wye is a switch connecting the North leg to the straight leg to the West.

But a standard switch doesn’t fit. When I first laid out that downtown wye section, I thought the Aristo-craft wye switch replaced a full 20′ curved segment of track. I found out the hard way it didn’t. Trying to fit those 14′ diameter curves to the diverging routes of the wye switch didn’t work as planned.

The angles were off just enough that it didn’t fit without having to resort to flex track and bending a tighter radius to make it fit. Without the wye switch in place, the 14′ diameter segments fit just fine. It may be better to redo that section to make it fit right while we already have it apart and all torn up anyway. We shall see…

Making Progress

Amazing what was accomplished in a single weekend. All of the elevated sections are in place and painted with the track repaired and installed. That was easy compared to what’s next. The ground level sections, starting with the mainline and siding switches to the station siding. And there’s a reason for starting there.

Because of the “hiccup” with the wye switch not quite aligning with the diverging legs of the wye, that becomes the most important location on the layout. Everything has to be measured against and fit to that point. Why? Because the station siding just fits using 10′ diameter curves and the two wide radius switches. And that has to be the starting point for the wye switch.

Another consideration is the height of the mainline crossing Main Street into Downtown. The original track height is too tall by about the thickness of a concrete block cap, roughly 1⅝”. The quick and dirty way around that in the past was to just line Main Street with concrete block caps, simulating curbing, sidewalks and building foundations.

It’s A Dirty Job…

Time to start digging out what remains of the rotted mainline and siding stringers. I need someplace to put all the dirt and gravel while test fitting the yet to be assembled replacements, but somehow I’ve managed to use all the five gallons buckets for something else.

A number of unused 16qt storage bins with lids are sitting in the garage, so they’re pressed into service. Fitting the new replacements fills two of them! I hadn’t planned on fixing anything more than the station siding, but as the digging exposes more and more of what remains of the other siding, the danger of exposed screws is apparent. Better fix it all while we’re in here.

Those 10′ diameter stringers have always been right at the edge of being too tight of a curve for any material, wanting to spring back to their original straight shape when removed from the jig. Thankfully we only need two sections (~60°), not an entire quarter circle (90°). It’s still straining to maintain its shape against the posts, and the screws are pulling out of the twisting spacers.

Repairing The Track

About as common as replacing rotted stringers is having to repair the track. It seems that just looking at the track wrong will cause the rail to pull out of the simulated tie plates and spikes. Now consider three good sized German Shepherd “pups” constantly pounding on them. Add to that constant UV bombardment from our hot Florida sun baking them brittle and prone to breakage.

Just about every piece of track needs disassembled and the tie strips “reseated” over the foot of the rails before the track can be put back in place. Anyone who’s ever dealt with those annoying little Aristo-craft screws knows what a pain they are. My big hammy hands make it even more difficult, inevitably losing some of those fumbly screws in the process.

In the past I’ve tried to patiently coax the ties back around the foot of the rail using tiny screwdrivers and other tools with limited success. What usually ends up happening is the another tie gets pushed off the rail while struggling to hold it in place and fix the first tie. Anyone that knows me knows what little patience I have doesn’t last long with fiddly things like that.

Relaying The Track

Anyway, each track section is laid back in its place as it’s repaired. SplitJaw™ rail clamps are then installed to connect it to the previous section. Learning from past mistakes, when securing a single tie with a screw to the stringer beneath, either the screw pulls through the tie or the tie gets ripped free from the rail, now uselessly still mounted to the stringer.

We recently switched to using zip ties every so often to hold several ties to an joiner block of the underlying stringer. It’s much more forgiving using this method. The track usually has enough give that it simply shifts to the side when absorbing impacts. That’s not to say that the track can’t still be damaged, but it certainly takes a lot more effort to do so.

Pulling the zip tie too tight is a quick way to cause damage.  The most difficult part is placing those zip ties when the stringers rest directly on the ground. It’s a struggle to feed them down through the ties, underneath the spacer block and then back up through the ties to secure them. But at least now the mainline and siding tracks are fully restored and in place.

What The Future Holds

Another weekend, another part of the Barkyard restored. The next big win would be to get the rest of the ground level track in place, including the rest of the wye. That’s most likely a future thing though. As it stands, the wye really isn’t a fully functional wye arrangement. The downtown loop doesn’t have the option of returning to downtown and looping back to the elevated sections.

It’s only connected to the straight leg of the wye using a 20′ diameter track section in place of the 14′ diameter section. That straight leg does have a switch at the other end, allowing trains to run along the lower loop around the deck and then along the South leg of the wye back to downtown and the mainline heading East.

What we need is a 14’/20′ diameter curved switch to connect the straight leg to the other leg of the wye. It’s not clear in those screen captures though. They don’t make 14’/20′ diameter curved switches. At least not that I’m aware of. There’s not enough room for anything else to fit. I’ve designed myself into a corner.

Spoilers

Back to the drawing board! Years ago I had started designing a home made #5 switch to connect a diverging 14′ diameter route with a 3′ long tangent route. I think I originally had the downtown wye in mind. I’ve put all the details in this post dedicated to the new switch design.

There’s a new discovery in there as well. One that could have MAJOR impact on Downtown! Let’s just say I can’t wait for my new 3D printer to get here! It’s due to arrive in the mid April timeframe. I ordered it back in November of last year (2025). Think of it as “next generation” printer technology compared to my other “first generation” technology printers, where everything is manual.

I’m looking forward to not have to manually swap spools of filament mid print while crossing my fingers that something doesn’t screw up. This new one can handle four different colors in one print. The printer actually supports up to 16 colors at once, but I opted for just the four in a single ACE cabinet to begin with. Not sure where I would put the other three ACE cabinets anyway.

For A Limited Time Only

I had been gathering the footage of the progress from the surveillance cameras, thinking they could be spliced together into a sort of time lapse montage. But then I missed the window to grab the footage from last weekend. I’m surprised by this since I’ve been able to go back more than a week in the past. I can’t remember the last time I wasn’t able to.

Oh well, I’m down to my last 3GB on a 4TB drive, not sure where I would have put it anyway! I was waiting for the 8TB NVME drive prices to come down, but with AI and all the global upending lately, that ain’t happening. It’s DOUBLE what it was last year! They want $200 more for the 4TB drive I already have! Also nearly double! And they want more AI and more data centers?

Don’t get me wrong. I’m not Grandpa Simpson shouting at the clouds. I’ve used AI in increasing capacities at work since before the Large Language Models (LLMs) emerged. AI has its uses, but it’s not the panacea it’s made out to be. It’s wrong more often than it’s right. And when it’s wrong, it still takes a human to detect those mistakes and retrain it to reduce their frequency.

At some point those rough cut videos will reappear, but not right now. We’re making too much progress toward getting trains running again.

 

Question? Concerns? Leave A Comment!

If you have any questions or concerns, please feel free to comment on this post. In any case, you’ll need to create a user account to do so. We don’t use any personal information for marketing or to spam you (see our privacy policy). We do it this way to avoid scammers spamming our posts. You’ll receive a verification email. Reply to the link provided to verify your email address. It’s all automatic. No waiting on moderator approval! No spamming your inbox with useless advertisements and “Special Offers”. None of that nonsense. We do it this way to prevent bots and spammers from detracting from your experience.

More to come. Stay tuned for Part II!

Happy New Year!

We hope you’re having a wonderful new year 2026. Ours is starting out in productive fashion, getting out in the Barkyard and getting things done! While I could make a list, I find my lists quickly become so detailed, they’re overwhelming by the time I’m done. But I’ll try to give the bullet points anyway.

Speaking of overwhelming, my lists pale in comparison to getting the Barkyard operational again. Now that the holidays and all the work that went in to getting the other house sold are in the past, it’s time to get back to work on the Barkyard. But at least we’re moving forward and not backward.

When I say backward, I’m talking about having to tear up track and remove rotted stringers, basically taking things apart instead of putting them together. It’s pretty bad when it’s been nearly a year since we’ve run any trains. I should probably check on that figure and see how long it’s really been… Time flies and all that.

Where Do We Go From Here?

So where do we start? Without getting into too much detail, all that backward momentum together with all that “stuff” that came over from the other house has consumed any space left in the garage. Bins and boxes of screws and nails and hardware and motorcycle parts and tools and… You get the idea. All the leftovers from the other house.

Now stack all that together, more like on top of, all the track and switches and PVC to make replacement stringers with and we’ve got quite the disaster of a mess to deal with before we can even think about gaining forward momentum again, let alone getting back to operation.

I’ve had my eye on a new shed. One that’s more than twice as big as the old one. I’ve even done some “what-if-ing” to see how I can fit something that big into our track plan without disturbing what we already have too much. After all, we’re trying to get things operational again, not tear up even more track!

A New Shed

There are a number of drawbacks to that new, larger shed. First is what to do with the old shed. Next is site preparation. Where the old shed sits now is already level. Who knows what we’ll run into preparing the new site? Then there’s the old fence that needs replaced first. And the dying tree behind the fence that needs cut down before that.

As much as I want that new shed, it’s a losing proposition when all the “has-to-be-done-firsts” are added up. Too many dependencies. Too many things to go wrong. All this before considering the large price tag that goes along with a large shed.

While we’re talking about disadvantages and drawbacks, the old shed has its own set. At slightly less than 7’x7′, nothing that’s longer than that can go in there unless it’s stacked tall instead of wide, like 4’x8′ sheet goods. Basically anything much longer than 6′ can’t lay down flat. It needs to stand vertically.

And now that I have those 8′ long stringers from the old HO layout that came over from the other house, they have to stand upright at the roof peak just to fit! But at least they do fit. But I’m getting ahead of myself again.

A New Shed!
A New Shed!

A Better Idea

Ann came up with a better idea, buy a smaller shed instead of that large one. That’s right. A smaller shed for just the lawn and gardening equipment. Because it’s smaller, it can sit next to the house along the driveway. Much more convenient than having to walk all the way to the back of the Barkyard for what’s needed in the front yard!

The Christmas blog was all about 3D printing all those snowmen, but we did a LOT more over the Christmas break than make Christmas presents for friends and family. Ann had a number of things on her list, and the new shed was only one of them!

Before the assembling the shed came the new shower doors. We managed to get those installed in a day. Less than a day actually. That in and of itself self is amazing. No yelling. No arguments. No harsh words or hard feelings. Just a sense of accomplishment and a Christmas present to ourselves that keeps on giving.

Assembling Ann’s new shed took the better part of the next day, but we’re two for two now. Two projects complete in two days! With that finished, Ann moved all the lawn and garden equipment from the old shed to her new one, freeing up much needed space for everything in the way in the garage, soon to have a new home in the old shed.

Skidding The Shed

Not so fast! First we need to replace the rotted plywood floor and framing under the old shed before everything can be moved to the shed. To do that, we need to skid the shed off of the rotted floor onto a set of 4x4s, then remove all that rotted wood to the curb for trash pickup. And before we can do that, we need to empty the shed.

That all goes smoothly. And quickly. We began to pull up the rotted plywood. But that left us with irregularly shaped pieces, too big to fit in the trash barrel. Turns out the plywood was so rotted I could use the flat shovel to chop it into small enough squares to easily bag up and drag to the curb. There isn’t much left of the 2x4s…

The site already level enough from when we first put the floor in place. That’s not accounting for any settling, but the HexPave will contain the gravel and gravel will pretty much self level itself once the shed is in place over it.

We decided to lay down landscape fabric to help keep the gravel from sinking into the sand. After that, it’s a matter of fine tuning the levelling and placement of the fabric and HexPavers. Finally the many bags of gravel get poured in and the new base is ready to skid the shed back in place.

Skidding the shed back over its new base proved to be much more difficult than skidding it off the old, rotted one. It takes repeated, coordinated, focused shoves from both of us to slowly nudge it into place. But once it’s done, it’s done. And done in a day no less! We both slept well that night…

Finally Moving In The Right Direction

And that’s what got the ball rolling. Finally. Forward momentum. And we managed to get it all done over Christmas break! Three projects complete in three days! Actually there were more than that, but those three were the big ones that mattered.

Now the stuff that’s always in the way in the garage can go out to the shed. All those leftover cabinet grade plywood pieces. All the storage bins full of plumbing pieces and parts under the long bench along the back wall now neatly fit on the shelf unit just inside the doors to the shed.

And now I can actually see the floor and vacuum up all the sawdust. That space freed up beneath the bench is now the home of the router table and other items from beneath the casting bench. That leaves room to get the old Super Magna engine up off the floor and on the shelf where the router table used to sit.

I’ll need to build a “crate” to mount that engine to and move it out to the shed eventually. But that can wait. It’s out of the way. Now I can deal with that bag of concrete we ripped open just trying to get the engine into the garage. Neatly tucked into a five gallon bucket, the stray dry mix on the floor gets vacuumed up along with that sawdust.

Stacks Of Snacks!
Stacks Of Snacks!

More Stuff?

All of that just to make room for more stuff. But that was the idea. The shed is already full and now the garage is overflowing yet again. And I still have more in the bed of the truck that needs a home! But there’s hope. Most of what’s in those bins can go in the garage wall cabinets or out to the shed once sorted through.

Now I can sift and sort through all the bins of this and that and whatnot that came over from the other house, no longer living in the bed of the truck, and organize it all together with like items already here. For expedience, all the motorcycle parts get condensed down into as few bins as possible and go straight to the shed.

That leaves room to sort through what’s left of the garage items in the large 90qt bins. Those are slowly condensed down into smaller 6qt and 16qt bins, freeing up a couple more of those 90qt bins. The trick is to find the time to do the sorting. I’ve taken a few lunch hours to get through a major portion of it.

The unspoken truth is there’s more than sorting to be done. Plenty of reorganization to the storage layout in the wall cabinets will go hand in hand with that sorting. The electrical items had already expanded from one to two cabinets. And now there’s more from the other house! Looks like the fasteners cabinet is due next.

Reorganization?

Thinking about it, all of them are due. I already have a few things in mind, like 3D printed saw blade storage and other such organizational aides, like 3D printed compartmental dividers to segregate all the raw materials to build trestles with into like sized pieces parts.

Speaking of those trestle parts, that was another major victory over the Christmas break. Moving ALL those containers with ALL those trestle building parts down from the shelf over the carriage doors and onto the bench. From there, the like sized parts were placed together in the bottom of a 90qt bin, using the 3D printed dividers to organize them.

Three things were soon apparent. First, the need for taller dividers. Second, the need for a second layer. Third, the 90qt bin is way too tall for the job. I searched for like sized, shorter bins and soon found a six pack of 41qt bins and ordered them. They’re about the same length and width, but much shorter. Just the ticket.

That frees up yet another 90bt bin. The only thing keeping this from completion is the lack of a layer divider of sorts. Those 3D printed dividers will need a redesign to make them more like stackable trays. Several containers of parts still sit on the bench until then, but it’s a good start.

The shelf space that freed up is now home to a multitude of 6qt and 16qt bins with seldom needed stuff, some already in the garage, and some moved there from the office now that there’s room for it. And it’s all up out of the way yet readily accessible using the short green ladder. Just add labels…

Stack Of Snacks!
Stack Of Snacks!

What’s Next?

Even with a stack of those large 90qt bins sitting in front of the table saw, there’s still much more room to move around in the garage. But enough about all the stuff in the garage already! What’s next? Preparing the taxes. Ugh. And acquisitions of course! Yay!

What do those have in common you ask? Not much, other than looking up eBay purchases for record keeping. And that sets the trap! Once on eBay, I’m reminded of all the things I was watching, like Aristocraft steam engines and other garden scale railroad items.

I’ll just briefly mention some of the items recently acquired. More to come in future posts! We already have two Aristocraft B&O Pacifics and a Milwaukee Road Mikado. Each has its own quirks and missing pieces. So why not add a third B&O Pacific as well as a New York Central Pacific?

And while we’re at it, how about three more Mikados? Two more Milwaukee Road and an oddball custom job that’s supposed to be a Grand Trunk Western unit. The most irritating thing about all of these is none of them included the tenders! I was hoping to score another Phoenix sound card in at least one of them, but no such luck…

I’ll save all the good stuff for the next post. And there’s plenty of it too!

Question? Concerns? Leave A Comment!

If you have any questions or concerns, please feel free to comment on this post. You’ll need to create a user account to do so, but we don’t use any personal information for marketing or to spam you (see our privacy policy). You’ll receive a verification email. Reply with the link provided to verify your email address. After that, it’s all automatic. No waiting on moderator approval! No spamming your inbox with useless advertisements and “Special Offers”. None of that nonsense.

More to come. Stay tuned!

Packing Up Decades Of Memories

The Current Situation

It’s the end of an era… The kids are finally all moved out of our home of 20 years in Wekiva. And even though Ann and I have been here in Mount Dora for more than a decade now, we still have more than two decades worth of memories stored there. Or rather, I still have memories stored there. Memories I have no place to store here in our two bedroom, single bath bungalow.

That all changes now that the kids moved into their own house. It’s heartbreaking when we look at what used to be our beautiful home of 20 years, only to see it totally run down, unloved all these years later. The kids never did much to make it their home. From the looks of it, they didn’t do anything. Not even basic maintenance. But enough said. The issue now is how much money our “retirement fund” is going to lose because of the state of disrepair it’s in now.

Perhaps lose isn’t as accurate as how much less money we’ll get now than we could have if it still looked as good as when it was our home. That’s not to say we couldn’t choose to hire contractors to fix her up, but we’d stand to pay as much to do that as we would get back from the boost in the sale price. Beyond that loss, add the immediate sting to our pocketbook to pay the price for someone to come do all those things the kids couldn’t be bothered to do for all those years.

Our home of 20 years - 10 years and $3500 of "deferred maintenance" later
Our home of 20 years – 10 years and $3500 of “deferred maintenance” later

More Distractions

Why does this seemingly never ending theme of always something else that needs done first matter? It’s really starting to wear on me. I’m ready to get things squared away in the Barkyard, but ever since my last post, I’ve literally spent every weekend over at the other house in preparation to list it for sale. Ann and Nick have spent even more time over there. Cleaning up all the trash and yard debris, but mainly getting the pool sparkling blue from thick green.

It’s a half hour trip there from Mount Dora. Multiply that by two trips, morning and night, and it adds up to two hours lost every day to nothing but travel, not to mention the fuel cost. Two hours a day that the kids spending two minutes a day could have saved us by simply checking the chemicals and cleaning the filter. But enough sour grapes. Soon it will be someone else’s treasure, ready to be transformed into their dream home.

We bought it as a “fixer upper”, with plenty of potential. When Ann first saw the view from the back yard, she said, “I don’t care what the inside looks like, we’ll take it”. We remodeled every room except for two of the bedrooms. We even remade the patio around the pool, adding a pool slide and a bar complete with a Gen-Aire grill. Now it’s someone else’s turn to take that potential and turn it into their treasure.

It would be different if my day job didn’t take every single minute I’m logged on from me, distracting me from what I’d rather be doing, working on my garden scale pike. The Barkyard has been on the back burner ever since I went back to work, more than three years ago. And for far longer than I ever imagined it would. And tragically, it shows! Plot twist, now my long lost HO scale empire is the reason it remains on the back burner.

My HO scale empire under construction in the corner room (circa 2006)
My HO scale empire under construction in the corner room (circa 2006)

Packing Up Memories

My job now is to get the corner room cleaned out and packed up. Everything I want to keep from what I’ve accumulated over a lifetime. I lost count of the number of trash barrels I filled with old and outdated computer and electronics parts. Magazines from the ’80s and ’90s. Basically a bunch of “stuff” that had a place there, but is no longer useful to me, or anyone else for that matter.

It breaks my heart to throw away all the chips and now otherwise useless components that were meant to be used in projects for my HO scale model railroad. Projects that never materialized. Hundreds, if not thousands of TTL logic level chips, like the 7400 series. Old 8 bit microprocessors and support chips. Even spare 8Kx8 replacement dynamic RAM chips from when I repaired my Commodore 64 after our home in Palm Bay was struck by lightning and zapped it.

Hopelessly Useless Discrete Integrated Circuits
Hopelessly Useless Discrete Integrated Circuits

With things today measured in gigabytes and terabytes, it seems comical to even think about something in the kilobytes. Parts with top speeds of ten or twenty megahertz can’t compete with today’s multiple gigahertz clock speeds. The really sad part is I can buy something off the shelf that’s already fully integrated and does what I want for a handful of dollars. Why would I waste my time designing and building it from discrete, obsolete parts?

Considering how much real estate a discrete component implementation would require compared to the postage stamp sized Arduino that could perform the same functions, and more, it’s a no brainer why these obsolete parts are now useless. The only exception would as replacements for failed parts in an obsolete piece of equipment. But then the question is how useful is that obsolete piece of equipment compared to its modern equivalent?

Decades of Memories - My Office "Dispatcher's" Chair (circa 2006)
Decades of Memories – My Office “Dispatcher’s” Chair (circa 2006)

My HO Scale Empire (Or What’s Left Of It)

A bit of history… I had a huge HO scale layout, spanning two bedrooms, one of which I called my office. The other used to be Nick’s bedroom, until he moved into his sister’s room when she moved out. I even cut tunnel passages through the drywall between the office and the corner bedroom. That all changed when we moved to Mount Dora and the kids moved back in there.

I’m hoping that just because I’m not talking about my garden scale pike, this HO scale discussion will still be of some interest. If not, it’s understandable. Anyone who’s ever started a model train layout knows it’s never finished. It’s a given. But this is going in the wrong direction entirely. Backwards. Having to dismantle everything I worked years to put together is not something I thought would be at the top of my priority list.

I had to dismantle the part of the layout that occupied my old office so our son-in-law could make it his office. That, too, was heartbreaking. Pulling up all the track and cork roadbed, removing track feeders, wiring and controllers. Then the real work began. Dismantling all the framework and carefully storing everything away in the corner room, with the understanding we would use that room for storage.

The plywood and L-girders were simply functional, meant to someday be covered with a beautifully stained veneer to match the ornate shelf brackets, with sweeping curves in the diagonal braces, crafted to mimic old railroad station architecture. Most of those pieces already made it to our Mount Dora home. The track and roadbed and HO scale structures remain there in the corner room.

Now defunct office side HO layout over the desk (circa 2006)
Now defunct office side HO layout over the desk (circa 2006)

The Last Of My HO Scale Empire

That was then. This is now. I had forgotten all the track and roadbed is still there on the bookshelf layout, high along the walls of the corner room. There are remnants of track and roadbed that remain where the coal mine used to sit on the main level along the wall to the office, complete with the holes for the tunnels in the drywall, still there after all this time. I patched them on the office side long ago.

Beyond all the trackwork, I have models of buildings and trackside structures, many of them kits still in their boxes awaiting assembly. The assembled structures I’ve had nearly my entire life, since grade school anyway. The coal mine for instance. The brewery. The rolling lift bridge. And many more. Those already assembled structures present the challenge of how to best store them in the smallest possible space… Without damaging them.

Beyond that are all the miscellaneous items, distributed across a diverse set of containers, including old Athearn blue boxes, assorted electronics cases, and even an old Dannon yogurt container. When I say miscellaneous, I mean tools, hardware, pieces parts of rolling stock, leftover model kit sprues, model train power packs, wiring, terminal strips, etc. Everything I’ve collected over the years for my HO scale empire.

From HO Scale Empire to Bare Office Walls
From HO Scale Empire to Bare Office Walls

Extraneous Information

So why all this extra information? To explain the lack of progress on the Barkyard. Why once again something else has taken higher priority. The good news is this “distraction” will help pave the way for our comfortable retirement. We stand to triple our money when we sell the house. Ann’s already retired. I’m not. I can’t wait, but I’ll have to, continuing to squirrel away 25% of my paycheck until then.

More good news is the progress in the garage here because of this distraction. Nowhere complete by any means, but many baby steps in the right direction. All the trestle making pieces are now in a large 90qt. storage bin, ready for organizer design and 3D printing. They were taking up all the “real estate” on the shelf over the carriage doors. Space that is now dedicated to storage bins that hold items seldom needed but not yet useless trash.

Some of those seldom needed items occupy most of the more valuable storage space above the wall cabinets over the work benches. While there’s not a whole lot of room to spare over the cabinets, what room there is would much better serve frequently needed items than seldom used ones. Items not used since going up “over the rafters” have been purged as well, making room for all the plastic stringer materials, just laying on the floor in front of the workbench.

Out of Garage Storage Space
Out of Garage Storage Space

Collateral Improvements

The garage is just one of the many “collateral improvements” underway, all thanks to needing more storage space. The only way to get there is to better organize the limited storage space available. Our Closet Lighting post details the addition of closet lighting, but doesn’t really touch on the amount of storage space that was freed up by cleaning out the closet.

The office has undergone a number of reorganizations too, incrementally wringing a bit more storage space here and there. But the biggest improvement yet was triggered by making space for the tall file cabinet coming here from the other house. The two “half sized” file cabinets have been here pretty much since we moved here. The time has come for the tall cabinet to move here too.

For the longest time, the color laser printer sat atop a stack of three large storage bins, full of HO treasures from previously dismantling the office portion of the layout. It sits at the end of the long stretch of cabinets in my office. This has a number of negative consequences. First is obstructed access, both to the bottom of the bookcase and the HO items stored in the bins beneath because of the printer sitting on top of them. Second is the lack of space for the printer anywhere else.

In preparation for that tall file cabinet’s arrival, the plan is to stack the two short cabinets atop one another and slide the tall cabinet in next to them. Same footprint on the floor, but twice as tall. Actually a little more than twice as tall, but you get the idea. There’s an assemble it yourself bookshelf unit that sits on top of the short cabinets at the moment, so the contents will need to go elsewhere and the shelf itself put out to the curb.

The Printer's New Home On Top Of The File Cabinets
The Printer’s New Home On Top Of The File Cabinets

Storage Improvement Phases

Now we get to a third consequence for the printer. Where does it get power? The wall outlet will be blocked once the file cabinets are in place. The solution is a new surge strip with a “wall hugger” cord, just long enough to reach the printer on top of the file cabinets. Phase one complete. Bookshelf gone, contents elsewhere, file cabinets stacked, and printer relocated. That eliminates one other negative consequence. Now the front panel is at eye level. And legible!

Phase two is sort through the HO treasures and reduce the bin count from three to two. The plan is to stack those two bins on top of the two large storage bins already in the corner of the bedroom next to my dresser. There’s room for six more bins, including the two everything gets sorted into now. Stacking them in the corner reveals these new 90qt. bins are larger than expected, but thankfully there’s still enough space for them.

My Model Building Retirement Stash
My Model Building Retirement Stash

Phase three is sort through the lower, sliding door section of the bookcase, now that moving those bins has restored access to it. There’s quite a bit of wasted space, even with all those CDs and DVDs in there. The original thought was access was seldom needed, so why not store them where access is difficult or limited at times. New plan. Move them elsewhere and store the plastic model kits in their place to take up that wasted space.

Those plastic model kits were the last things to come over from the other house and are now sitting on top of the bookcases. While all of them may not fit in that lower space, most of them will, freeing up the space on top for things that need more frequent access. Those models will have to wait until I have the time to spend on them. Like once I’m retired. At least, that’s the plan.

Model Kits' Temporary Quarters
Model Kits’ Temporary Quarters

Future Distractions

Eventually I want to “remake” the bookcases. Those bookcases were designed and built to be “massive”, because they occupied either side of the massive stone fireplace at the other house. And while they do provide a huge amount of storage space, they were never designed to fit the space they occupy. If anything, the exact opposite is true. The space they occupy was designed to fit around them.

Where they sit now influenced the size and design of the new bedroom closets here in Mount Dora before they were even built. Each bookcase is 32″ wide. I allowed a bit over twice that, 65″ total, to leave some “wiggle room” between the outside wall and the back of the closets. When the closets and the back porch remodeling were finally completed, it was apparent I’d forgotten to take into account the width of the baseboards and the bookcase trim pieces.

Massive Bookcases Bracket The Massive Stone Fireplace
Massive Bookcases Bracket The Massive Stone Fireplace

Some “minor” rework with a backsaw and problem solved. The larger problem is how to redesign them to better suit that space? Maybe it’s better to say rework them into a design that reuses as much of them as possible, if possible. The bookcases aren’t quite 22″ deep, and there’s only about 18″ between the end of the cabinets the bookcase on that side. Where they meet is a blind corner cabinet situation.

The main (structural) shelf is lower than the cabinets too, 30″ vs. 36″ off the floor, so simply extending the countertop to the bookcases won’t work. But that’s a future distraction. If it’s not apparent by now, it should be obvious why it takes so long to get anything done on the Barkyard. In this case, coming up with the design, finding a place for everything sitting on the bookcases, then disassembling and reassembling them to match the design.

The Next Distraction

Unfortunately, the next higher priority item is filing the taxes. We always file for an extension, which is why the deadline is October 15th, and not April 15th as you would expect. Hopefully it goes quickly and smoothly. As much as preparing for the sale of the house has been a source of friction between Ann and myself, it doesn’t hold a candle to tax time. It’s always guaranteed to bring those “suppressed emotions” to the surface.

Always something else that needs done first!

Taxes Due!
Taxes Due!

Leave Us A Comment

If you made it all the way through to the end of this post, thank you. I hope you understand why this is important to us. Even if we didn’t really discuss the Barkyard all that much, other than to explain why we still have no progress to show all this time later. Call them excuses. Call them what you will. Soon we’ll have all the time that was taken from us by everything else that was higher priority.

In any case, leave us a comment to let us know what you think. You’ll need to create a user account to do so, but we don’t use any personal information for marketing (see our privacy policy). You’ll receive a verification email. Reply with the link provided to verify your email address. After that, it’s all automatic. No waiting on moderator approval! No spamming your inbox with useless ADs and Special Offers. None of that nonsense.

Stay tuned…

 

Infrastructure Improvements

We’ve made a number of improvements over the Summer. Some we’ve already covered. Some not. We’re making progress, albeit slowly. The main focus is getting trains running again, and to do that, we need to start laying track again, not pulling it back up.

Something that’s been bothering me is the lack of progress on setting the last batch of roadbed bricks in place. It’s been a couple of months since the last batch of bricks was cast and laid in position. That’s mostly on me for not improving the state of the garage. It’s in no shape to work on any project. Not until recently anyway.

I’ll save how the garage and the office were updated with new shelving and other improvements for another post. To say the least, the casting bench is ready for action. And speaking of casting, it’s time to set those roadbed bricks in place then cast more and place them.

Some Filaments Are More UV Resistant Than Others
Some Filaments Are More UV Resistant Than Others

If you remember from the Roadbed Bricks – Round Three post, some of those 3D printed ballast profile molds had warped and yellowed from the UV exposure. What’s left of them are sitting in a bucket outside the carriage doors of the garage. So the “then cast more” part is going to have to wait.

Setting The Bricks

We’ll get back to that later. Now it’s time to set the rest of those bricks in place. They’ve been lying there on top of what’s left of the artificial turf that needs cut back to make room for them. Time to better protect that 14# power feed cable in the process by “hiding” it under the turf next to the bricks.

My “wheelie cart” helps save me from having to crawl around on my hands and knees. Lately my knees painfully remind me I’m not getting any younger. In the spirit of “there’s always something else that needs done first”, the tires need inflated. They’re not quite flat, but they could definitely use some air.

My Helper As Always
My Helper As Always

I grab the Dremel saw bag and the retractable extension cord and get that ready to go while waiting for the compressor to build up pressure. The retractable air hose makes it easy to fill the tires just outside the side garage door. Much better!

The first thing I find once I get going is most of the four bricks are already sitting right on the dirt. If it weren’t for that black “weed control” fabric and just a wedge of turf, they could be set right in place, if the dirt had been moved anyway. Time for the yard cart… Which is full of water!

Well, not all the way full, but Hurricane Debby dropped a good amount of rain on us. Easy enough to dump it out and roll it over to the job site. I made sure when I ordered the new Gorilla Cart™ it came with the solid tires. No worrying about flats!

A couple of quick cuts with the Dremel saw make quick work of that turf wedge. And the black fabric can be pulled out of the way enough to set those first four bricks in place. It takes a few tries to remove enough dirt and test fit the contour for each brick.

The First Four At The Job Site
The First Four At The Job Site

Annoyances

That fabric certainly is annoying though. Not only does it NOT stop the weeds from growing, it’s so flexible it’s nearly impossible to cut with the Dremel saw! The one thing it DOES do well is keep the seams between the sections of turf from “puckering”, for lack of a better term.

Puckering describes the way the dirt washes away at the seam and builds up under either side, like lips puckering. At this point, it’s no longer necessary with the bricks in place. The work progresses a brick or two at a time while cutting away the turf and fabric and fitting them in place.

By the time I’m finishing up, the shade has disappeared. The new umbrella Ann got me is working fine to block the sun though. It wouldn’t have taken so long if it weren’t for the post and remnants of the stringer that were in the way and had to be removed.

The Stretch To The Switch Set In Place
The Stretch To The Switch Set In Place

Unfortunately that left a patch of dirt exposed leading up to the switch. Thankfully a chunk of turf previously cut out of the way covers it and fits the bill quite nicely. It will be good enough until the next batch of bricks is ready to finish that stretch.

But Wait, There’s More

But it’s not done yet. There are three more bricks on the other end of the “cast in place” failure. Alright, it wasn’t a total failure, but it ain’t very pretty and that’s for sure. These three fit between the other end of the “cast in place” section and the end of the previous batch of bricks.

It’s a bit harder to get the turf cut this time because of the surroundings. On one end is the the previous batch of bricks and the other is cast in place concrete. But the most difficult part is the tight squeeze getting everything to fir in that space!

That end brick from the last batch actually had the corner crack off, but it doesn’t want to go back in place without a fight, or leaving a gap. After more finagling, and even more stomping, they finally fit. Probably best not to disturb the bricks already placed last time around.

The Last Of The Batch Set In Place
The Last Of The Batch Set In Place

Levelling Up

Next up is levelling that 4×4 that sits proud of the first batch of bricks. All those 4x4s along the lower loop started out level when first installed. Over time they settled, heaving or slumping in the process. Every one of them sit on dirt with the exception of the one sitting proud.

That 4×4 sits proud because it’s resting on a wedge of turf. A wedge of turf that should have been cut out of the way when it was first installed a few years back. The time has come. But first the 10′ section of flex track that sits on top of it has to be removed.

This allows access for refitting the 4×4 to sit lower and level with its neighbor and the first round of bricks. Turns out not only is there one wedge, there’s two! A convergence, where two different sections of turf meet. This discovery forces removing the first batch bricks, disturbing the pile of rubble they sat on.

After struggling with getting the high spot out of the middle and trying to eliminate the rocking motion, the 4×4 finally sits flat and at the proper level. Getting that rubble and the bricks to sit flat and level is even more of a struggle, but eventually everything lines up.

Many Infrastructure Items Resolved
Many Infrastructure Items Resolved

More Levelling

Unfortunately that 4×4 wasn’t the only one that needed attention. Ann had been working in the front yard, adding pavers and removing dirt to do so. She nearly filled the dump cart and I dumped that dirt where the track leaves the deck. The idea is to build up the terrain there.

After removing the section of track, I backed the heavy dump cart over the 4×4 and released the latch to dump the dirt. Why does this matter? Those aren’t the 4x4s that need levelled! It’s the ones in front of the deck step. Yet another 10′ section of flex track needs moved.

Thankfully this time the turf didn’t need trimmed, but it did need pulled out of the way while adjusting the 4x4s.  While I still have the track out of the way, it’s time to trim the turf along the 4×4 that staircases the terrain where the dirt was dumped.

Dirt Terraced And Track Laid On Levelled 4x4s
Dirt Terraced And Track Laid On Levelled 4x4s

The cutoff piece of turf isn’t quite big enough cover all the dirt, there’s still an exposed patch, but it’s mostly covered. Time to put the track back together. Of course, the Split Jaw™ couplers needed new socket head bolts to replace the bent, mangled originals.

Thankfully the track just falls into place, having retained their shape from using the rail bender when they were first installed. The hold down screws are left out for now with the idea that some 1×2 blocking will be fabricated to hold the rail in place.

For now, even the end that was uneven drops right into place. It doesn’t even take concrete blocks like it did months ago. It probably would have waited, except the Bozos that installed the new copper A/C line set grabbed them and used them for seats and step stools.

The Track Finally Fits The Roadbed Bricks
The Track Finally Fits The Roadbed Bricks

Sour Grapes

Definitely some sour grapes there. First of all, who told them they could use those blocks? And they didn’t even put them back where they got them! I had to download the security camera videos just to know whether they took them with them when they left.

Second, but more importantly, who misdiagnosed the leak was in the line set to begin with? Nothing like having to pay $1500 for a non repair! Still leaking and no A/C a day later, in Florida, in the middle of August no less! Ends up needing a brand new condensing coil and we get to pay to have that installed too!

Guess I should be happy we finally got someone that knew what they were doing. So frustrating paying supposed “professionals” to have it done right and I end up knowing more than they do! I’m paying you to fix it so I don’t have to!

Broken Stringer And Extra Track Removed
Broken Stringer And Extra Track Removed

But enough whining. I don’t need them to hold the track down anymore, and that was the goal. To keep the puppies from poking their eyes out, I removed the sagging 3′ straight track section and the broken stringer that was no longer holding it up.

I left the plastic pipe to mark where the track goes in preparation for the upcoming trestle work. You can see from the pictures how much more track work remains. Next step is to add back more of the 10′ flex track sections into the roadbed bricks.

Still struggling with the decision to use wooden or metal for the trestle and bridges. It may end up being 3D printed PETG that looks like metal, but still have to experiment with PETG and its durability when exposed to the elements. Time will tell.

“Then Cast More”

I promised to say more about the “then cast more” part of the discussion. One of the things accomplished when making the casting bench operational was to cut the 8′ long pieces of the roadbed brick casting forms into two sets 4′ long.

They’re sitting on the casting bench waiting to be reassembled. I’m still looking for another chunk of 2×6 that’s 4′ long to create a third 4′ long form. I’ve also 3D printed at least three more ballast profile molds for that section, but will probably need more

More to come, so stay tuned!

 

 

 

 

 

 

 

3D Printed Casting Mock Ups – Round Two

This is a short follow up on the original 3D Printed Casting “Mock Ups”. Considering the length of the original post, that’s an understatement. But sometimes it’s necessary to fill in the blanks when progress is low and discouragement is high.

Even though progress has been slow, it’s actually been beneficial in this case. The original design is based on our “fleet” of Bachmann passenger cars, literally dozens and dozens and dozens of them. Some modified with our Passenger Car Lighting systems, some still sporting the original 9V battery twin light bulb version. All of them suffering from flimsy, rubberized plastic handrails.

I wouldn’t mention those handrails except we’re talking about 3D printing. What better replacement for plastic than plastic? Well, metal for one. Brass to be exact, but then we’d need jigs for bending the brass to shape, most likely 3D printed as well.

Steps Barely Clear Capstones
Steps Barely Clear Capstones

Design “Flaws”

Just like those original handrails that failed the test,  so did our original casting design. Well, at least the mock up did. The first flaw was discovered when first fitting the 10′ diameter curved track section. A redesign doubled the number of segments to better fit the curve. This was discussed in the first installment and it works quite well.

The next “flaw” is genuinely a “new” one, as in there’s not enough clearance for the new USA Trains Heavyweight passenger cars. And before you ask, no, there are not dozens of them. But there is a decade of them. There was a bulk deal on ten of them around Christmas time, so I pulled the trigger, as well as ordering a pair of F7 A-B units for A-B-B-A running.

They’ve been packed away since then, awaiting completion of all these “infrastructure improvements”. After unboxing one of them to test with, it was readily apparent the design was too narrow for these behemoths. The car is longer than the mock up! The wheels just fit on a single curve section though.

The steps and the equipment boxes both will interfere with the platform or the capstones. Back to the drawing board! It took some doing, and some days to do it, but I managed to add a “crude” approximation of the new passenger car to the mock up design.

Steps Interfere With Pillar Capstones
Steps Interfere With Pillar Capstones

Back To The Drawing Board

The test fit also reveals a flaw in the “track trough”. Not sure where I picked up that fault, but for whatever reason, the track is sitting proud of the platform rather than flush with it. To give an idea of how the prototype fits together, most platforms are slightly higher than the track, by about 4″ (10cm). In scale, that’s roughly 1⁄6″.

I figured giving the equipment that little bit of a height boost would hopefully compensate for any errors made while measuring their dimensions. Looks like I worried about the wrong measurement errors. Add that to the list of things that need fixed.

I’m back and forth with whether to try to forcibly disassemble the mock ups or just print all new pieces. I say try because the chemical solvent I use to cement the plastic pieces literally melts the two together into one part. Printing all new pieces is going to take a lot longer.

Each 4″ x 7″ retaining wall segment takes 4½ hours to print. Two of the pillars that join the wall segments take 3½ hours. An 8″ long track trough takes 5 hours. It should have been obvious when the curved track trough only took 3½ hours to print.

Anyway, these flaws are certainly obvious now. Not to worry though, the entire reason for all these mockups is to find the errors and flaws before they’re cast in stone, er… concrete.

Time Better Spent As Debby Approaches
Time Better Spent As Debby Approaches

Time Is Of The Essence

Alright, being overly dramatic, but time certainly is the essence of the conundrum. As in there is not enough of it to get ahead of everything that needs done. So little to do and so much time… Strike that. Reverse it.

Some say if deadlines are not set, they’ll never be met. Tell that to hurricane Debby. Now instead of spending time moving closer to the goal of running trains, it will now be spent preparing for a hurricane.

Retract the SunSetter™ awning. Stash any loose items that will blow away, like lawn chairs and cushions. You get the idea. Now add to that the garage where those items are usually stored is still the disaster it was right after the A/C decided to leak all over everything.

Progress is slow, but progress is progress. The large empty storage bin that used to sit in front of the table saw because there was no place else to put it is now filled with HO scale items that used to occupy a slot on the bookshelves in the office. It will fit beneath the work cell, taking up the wasted space under it.

Next Steps

Immediate steps are hurricane preparation, like dumping the work cart full of dirt at the end of the driveway where it has washed out around the apron and sidewalk, then retract the awning so as not to create a cart full of mud.

Beyond the immediate, back to the drawing board. The track trough and curved section redesign has already begun, old hold temporarily to prepare for Debby. I don’t like leaving the 3D printer sit idle for any length of time, but short of printing more 4″ x 7″ retaining walls, it will have to wait for the new part designs.

The big ticket item is capturing the step by step process for actually creating the station platform from all the separate cast pieces and how to create forms with them for a concrete pour. So far the mockups have captured segments of the final product, but not the process of creating those final products.

The garage needs a few more items completed before it’s ready for casting concrete patch into those retaining wall panels. There’s a stud space or two where the sill plate is totally rotted that could use a new chunk of 2×4 before setting the table saw in front of there.

The new shelves are already installed but need some thought put in to organizing what should go there and what will fit. All the things that haven’t been used and won’t be any time soon were thrown out to make more space.

It continues to evolve, like the wall cabinet for electrical items expanding to occupy two cabinets. Next is going through that cabinet that has all the “might be useful” items for the model railroad, ripe for harvesting more trash that will never be used.

Long Term

Long term is 3D printing with PETG, a more suitable material for use outdoors. Definitely more heat resistant than PLA. Not sure about its UV resilience, but paint can mitigate any shortcomings there.

The first designs will be concerned with ties and insulated split jaw parts. The originals printed in PLA lasted about ten minutes before they started to melt and deform in the Florida heat. Those stainless steel rails get mighty hot in the sun!

Next will be structural items, like window and door frames, “gingerbread” decorations and supports on buildings, etc. The ultimate goal is to create our own switches and turnouts, custom fit to the needs of the Barkyard Railroad.

Stay tuned. Much more to come.